12/02/2020
-
created by
Jan Niklas Grieb on 12/02/2020 12:37 AM
12/01/2020
-
updated by
Jeremy Hansen on 12/01/2020 10:35 PM -
Comment added
Experiencing the exact same issue:
https://community.openproject.com/topics/12873?r=12898#message-12898
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 09:01 PM -
Comment added
Here seem to be some examples where the same or something similar happened:
https://community.openproject.com/topics/127...
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 08:59 PM - The changes were retracted.
-
updated by
Max Mutzge on 12/01/2020 08:41 PM -
Comment added
A user had an idea on how to achieve such functionality, it seems: https://community.openproject.com/topics/12880
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 08:29 PM -
Comment added
As this is time-critical I assigned it to the upcoming release
- Version set to 11.0.4
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 08:25 PM -
Comment added
I set "requires docs changes" to "Yes" because we need to document the behavior of the search feature.
- Subject changed from Search-function woks not reliable to Search doesn't find documents or text within documents
- Description changed (Details)
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 08:22 PM -
Comment added
Regarding the first and second case:
It seems like the search only finds documents that are named like the section of th...
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 07:43 PM -
Comment added
A customer reported this or something similar, too (in the wiki). So far I couldn't reproduce it again, though.
- Type set to Bug
- Project set to OpenProject
- Subject set to Image disappears when using "Insert image" feature
- Description set (Details)
- Status set to new
- Priority set to Medium
- Author set to Max Mutzge
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- File grafik-4.png added as attachment
- Requires doc change set to No
- Bug found in version set to 11.0.x
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 06:08 PM -
Comment added
+1 from a customer and a trial user. Both of them are using Clockify at the moment and want to track time easily within ...
- Votes changed from 5 to 7
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 05:33 PM - Status changed from new to closed
-
updated by
Benjamin Bädorf on 12/01/2020 04:57 PM - Description changed (Details)
- File image__6_.png added as attachment
-
updated by
Robin Wagner on 12/01/2020 01:20 PM - Description changed (Details)
-
updated by
Robin Wagner on 12/01/2020 01:03 PM -
Comment added
Thank you for the refactoring. It looks really good.
Here are some issues / suggested improvements:
Bugs:
Cells in the ...
- File image.png added as attachment
- File image.png added as attachment
- File Bug_Create-WP-List.gif added as attachment
- File image.png added as attachment
- File Bug_Cell-properties-width-height.gif added as attachment
- File Bug_Cell-Highlighting.gif added as attachment
-
Comment added
-
updated by
Max Mutzge on 12/01/2020 12:10 PM - Description changed (Details)
- Requires doc change set to Yes
-
updated by
Max Mutzge on 12/01/2020 12:06 PM -
Comment added
Specified in collaboration with RW, therefore setting new status and moving to Product Backlog
- Description changed (Details)
- Status changed from new to specified
- Assignee deleted (
Max Mutzge) - Version changed from Wish List to Product Backlog
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 11:38 AM -
Comment added
Those need to be cleared even though there are no schema changes to get the seeding fix in, Markus Kahl
- Subject changed from (Optional) Clear free (buffered) trial tenants on saas after deployment and replace with fresh ones in case of schema changes
to Clear free (buffered) trial tenants on saas after deployment and replace with fresh ones in case of schema changes
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 11:37 AM -
Comment added
We will need no downtime.
- Status changed from new to rejected
-
Comment added
-
updated by
Robin Wagner on 12/01/2020 11:34 AM -
Comment added
Thank you Jens Ulferts, Markus Kahl .
I tested it and it works properly on newly created stage environments.
- Status changed from test failed to closed
- Assignee deleted (
Robin Wagner)
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 10:32 AM - Type set to Task
- Project set to OpenProject
- Subject set to Gather feedback on WYSIWYG changes
- Description set (Details)
- Status set to new
- Priority set to Medium
- Version set to 11.1.0
- Author set to Jens Ulferts
- % Complete set to 0%
- Parent set to Optimierung des PDF Exports für Wiki-Seiten
- Scheduling mode set to Automatic
- Working days set to include non-working days
-
updated by
Benjamin Bädorf on 12/01/2020 10:19 AM - Description changed (Details)
-
updated by
Jens Ulferts on 12/01/2020 09:52 AM -
Comment added
Seems to be working now on stage. Can you please double check, Robin Wagner ?
- Assignee changed from Markus Kahl to Robin Wagner
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 09:43 AM - Status changed from tested to closed
-
updated by
GitHub on 12/01/2020 09:40 AM -
Comment added
PR Opened: Pull request 8862 fix copying with overwritten costs for opf/openproject has been opened by ulferts.
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 09:38 AM - Version changed from 11.0.4 to 11.1.0
-
updated by
Jens Ulferts on 12/01/2020 09:01 AM -
Comment added
Will not make it into 11.0.4.
- Version deleted (
11.0.4)
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 09:01 AM - Assignee changed from Benjamin Bädorf to Markus Kahl
-
updated by
Jens Ulferts on 12/01/2020 09:00 AM -
Comment added
This counts as tested. Whether the translations exist in all of the languages cannot be guaranteed by code.
- Status changed from test failed to tested
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 08:58 AM -
Comment added
user#67841 the limitations of the labels are accepted by the customer. Getting this to a perfect solution, where the lab...
- Description changed (Details)
-
Comment added
-
updated by
Jens Ulferts on 12/01/2020 08:25 AM -
Comment added
Hi Robin Wagner,
I assume it was simply because there where prepared database instances still in the queue. Markus Kahl ...
-
Comment added
11/30/2020
-
updated by
Robin Wagner on 11/30/2020 05:57 PM -
Comment added
Hi Jens Ulferts, hi Markus Kahl,
Matthias and I tested 11.0.4.
There are some errors but nothing critical that would pr...
- Status changed from in progress to closed
-
Comment added
-
updated by
Max Mutzge on 11/30/2020 05:44 PM -
Comment added
Great! I'll close this, then.
Thank you for the answer!
- Status changed from needs clarification to rejected
-
Comment added
-
updated by
Max Mutzge on 11/30/2020 05:41 PM -
Comment added
Hi Frank,
thanks for the feature request! I moved it to the wish list to evaluate it.
Kind regards
Matthias
- Version set to Wish List
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 11/30/2020 05:39 PM - The changes were retracted.
-
updated by
Robin Wagner on 11/30/2020 05:25 PM - Description set (Details)
- Status changed from new to in progress
-
updated by
Robin Wagner on 11/30/2020 05:04 PM -
Comment added
Adding to 11.0.4 since this error may be related to OP-7784. Feel free to move to a future version.
- Type set to Bug
- Project set to OpenProject
- Subject set to Copy budget: Manually set cost are set back to cost deduced from number of units
- Description set (Details)
- Status set to confirmed
- Priority set to Medium
- Version set to 11.0.4
- Author set to Robin Wagner
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- File Bug_Copy-budget.gif added as attachment
- Requires doc change set to No
- Bug found in version set to 11.1.x
-
Comment added
-
updated by
Robin Wagner on 11/30/2020 05:03 PM -
Comment added
Thanks for reporting and addressing this, Boris - and Jens.
Copying a budget works now without a 500 internal error. Tha...
- Status changed from merged to closed
-
Comment added
-
updated by
Robin Wagner on 11/30/2020 04:39 PM -
Comment added
Hi user#67287,
This error still seems to occur. I just tested it on a newly seeded stage environment (which runs 11.0.4)...
- Status changed from merged to test failed
- Assignee set to Benjamin Bädorf
- File Bug_edit-default-widgets.gif added as attachment
-
Comment added
-
updated by
Robin Wagner on 11/30/2020 04:28 PM -
Comment added
Works properly on stage.
- Status changed from merged to closed
-
Comment added
-
updated by
Robin Wagner on 11/30/2020 04:25 PM - Status changed from merged to tested
-
created by
Stuart Connor on 11/30/2020 03:17 PM -
updated by
Max Mutzge on 11/30/2020 02:31 PM -
Comment added
Jens Ulferts could you please remove the "Acceptance criteria still to be discussed" so that nobody gets confused whethe...
- Status changed from merged to tested
- Assignee changed from Max Mutzge to Aleix Suau
- File
image.pngremoved as attachment - Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 11/30/2020 02:29 PM -
Comment added
Works on Edge, also for another work package type that is defined as milestone.
If two Milestones are too close one of t...
-
Comment added
-
created by
Benjamin Bädorf on 11/30/2020 02:26 PM -
updated by
Philippe de LUSSY on 11/30/2020 01:54 PM -
Comment added
Hello I confirm the same , version OpenProject 11.0.3 (PostgreSQL) on Docker.
BUT "only" is the user has non english set...
-
Comment added
-
updated by
Jens Ulferts on 11/30/2020 01:47 PM - Finish date changed from 11/30/2020 to 12/02/2020
- Start date changed from 11/30/2020 to 12/02/2020
-
updated by
Jens Ulferts on 11/30/2020 01:47 PM - Finish date changed from 12/15/2020 to 12/17/2020
- Start date changed from 12/15/2020 to 12/17/2020
-
updated by
Max Mutzge on 11/30/2020 01:45 PM -
Comment added
Stage:
German: Manage overview page
English: Manage overview page
Italian: Manage overview page
French: Gérer la page d'...
- Status changed from merged to test failed
- Assignee deleted (
Max Mutzge)
-
Comment added
-
updated by
Mario Tschunke on 11/30/2020 01:27 PM -
Comment added
+1 from user evaluating different project management solutions.
We need Multi-project resource management in our organi...
-
Comment added
-
updated by
Aleix Suau on 11/30/2020 10:19 AM - Description changed (Details)
-
updated by
Aleix Suau on 11/30/2020 10:00 AM - Description changed (Details)
-
updated by
Aleix Suau on 11/30/2020 09:53 AM - Description changed (Details)
-
created by
Birthe Lindenthal on 11/30/2020 09:51 AM -
updated by
Robin Wagner on 11/30/2020 09:31 AM -
Comment added
Since I tested the duplicating work package (#35339) on qa-stage, I'll change the status of this work package as well.
W...
- Status changed from merged to closed
- Assignee deleted (
Max Mutzge)
-
Comment added
-
updated by
Rainer Proehl on 11/30/2020 07:28 AM -
Comment added
+1 from potential enterprise customer
-
Comment added
11/29/2020
-
updated by
Max Mutzge on 11/29/2020 11:43 PM - Subject changed from Option to set available work package types in project settings visible for users not allowed to edit them
to Option to set available work package types in project settings is visible for users who are not allowed to edit them
- Subject changed from Option to set available work package types in project settings visible for users not allowed to edit them
-
updated by
Max Mutzge on 11/29/2020 11:40 PM - Subject changed from Sett the buttons below comment field further apart or/and make them bigger to Set the buttons below comment field further apart or/and make them bigger
11/27/2020
-
updated by
Aleix Suau on 11/27/2020 08:02 PM - Description changed (Details)
-
updated by
Robin Wagner on 11/27/2020 07:57 PM -
Comment added
Hi Jens Ulferts ,
As a quick update: The main objective would be to display the Kanban board in a more "compact" way.
Th...
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 05:22 PM -
Comment added
+1 from user
- Votes changed from 26 to 27
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 01:04 PM - Subject changed from Apply grouping to XLS export for time and costs to Apply grouping to XLS export for work packages
- Description changed (Details)
- File image.png added as attachment
- Votes changed from 4 to 2
- Reach changed from 1.5 = Small reach (~5% to ~25%) to 3.0 = Significant reach (~25% to ~50%)
-
updated by
Robin Wagner on 11/27/2020 01:02 PM -
Comment added
Transferring votes wrongly assigned to OP-5158.
- Votes changed from 1 to 3
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 12:48 PM -
Comment added
Reach: Limited to users working with Time and Costs
Impact: High, since users want to often export the exact view they c...
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 12:42 PM - Votes changed from 3 to 4
-
created by
Frank Schmid on 11/27/2020 12:11 PM -
updated by
Markus Kahl on 11/27/2020 11:10 AM - Votes set to 3
-
updated by
Robin Wagner on 11/27/2020 10:33 AM -
Comment added
Also requested by other user.
- Votes set to 2
-
Comment added
-
updated by
Max Mutzge on 11/27/2020 10:15 AM -
Comment added
Reported by a user. I think it would make sense to apply this to every place where these confirm and abort buttons are u...
- Type set to Feature
- Project set to OpenProject
- Subject set to Sett the buttons below comment field further apart or/and make them bigger
- Description set (Details)
- Status set to new
- Priority set to Medium
- Author set to Max Mutzge
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- File image.png added as attachment
- Requires doc change set to No
-
Comment added
-
updated by
Max Mutzge on 11/27/2020 09:59 AM -
Comment added
Hi Frank,
thank you! I updated the description accordingly.
Kind regards
- Description changed (Details)
-
Comment added
-
updated by
Max Mutzge on 11/27/2020 09:43 AM -
Comment added
Hi Harald,
thank you for the explanation! I'm sorry, it seems I didn't pay enough attention when looking at the screensh...
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 09:39 AM -
Comment added
user#67841 , could you test this on qa-edge please?
Thanks a lot,
Robin
- Assignee set to Max Mutzge
-
Comment added
-
updated by
Robin Wagner on 11/27/2020 09:37 AM -
Comment added
user#67841 , could you test this on qa-stage please?
Thanks a lot,
Robin
- Assignee set to Max Mutzge
-
Comment added
-
created by
Daniel Meiler on 11/27/2020 09:36 AM -
updated by
Robin Wagner on 11/27/2020 09:36 AM -
Comment added
user#67841 , could you test this on qa-stage please?
Thanks a lot,
Robin
- Assignee set to Max Mutzge
-
Comment added
-
updated by
Samantha Machon on 11/27/2020 09:14 AM - Votes changed from 2 to 3
-
updated by
Various Interactive on 11/27/2020 08:06 AM -
Comment added
Hi user#67841,
it is not in the Detail view. It is in the overview (list view of the work packages). Yes the person is m...
-
Comment added
11/26/2020
-
updated by
Anton Motovilov on 11/26/2020 08:41 PM -
Comment added
All, ok. Need run worker cron!!!
-
Comment added
-
updated by
Benjamin Tey on 11/26/2020 08:35 PM -
Comment added
Hi Matthias,
Kanban WIP Limits is a value that limits (min/max) the number of "cards" in a kanban list. WIP corresponds ...
-
Comment added
-
updated by
Benjamin Tey on 11/26/2020 08:17 PM -
Comment added
Hi Matthias,
Kanban swimlanes is the option to group cards horizontally by other fields. This is an example image:
https...
-
Comment added
-
updated by
Frank Schmid on 11/26/2020 08:04 PM -
Comment added
Hi user#67841,
first of all, thanks for your answer.
No it is not quite the same as ticket OP-4702.
What is my goal:
We ...
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 07:21 PM - The changes were retracted.
-
updated by
Max Mutzge on 11/26/2020 07:15 PM - Assignee deleted (
OP Dev All) - Requires doc change changed from No to Yes
- Assignee deleted (
-
updated by
Max Mutzge on 11/26/2020 07:13 PM - Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/26/2020 07:10 PM -
Comment added
Another customer reported this (similar case):
He/she pastes the images directly into the text editor of the work packag...
- Status changed from new to confirmed
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 07:06 PM -
Comment added
Hi Anton,
do emails for work package updates get sent?
Could you solve this in the mean time?
Kind regards
Matthias
- Status changed from new to needs clarification
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 07:02 PM -
Comment added
Hi Walid, as far as I see it this is no actual bug. I changed the type to a feature request. If you want to add somethin...
- Type changed from Bug to Feature
- Description changed (Details)
- Status changed from confirmed to new
- Version set to Wish List
- Bug found in version deleted (
11.0.x)
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:58 PM -
Comment added
This is the same for attendees, not only for the host
- Description changed (Details)
- Status changed from new to confirmed
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:53 PM -
Comment added
I could reproduce this:
I created a new project and new tasks. The same error appears, regardless whether the tasks had ...
- Subject changed from Copy more than one Workpackage and remove assigned person creates error to Not able to bulk-copy and set assignee to "nobody"
- Status changed from new to confirmed
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:39 PM - The changes were retracted.
-
updated by
Max Mutzge on 11/26/2020 06:38 PM - Finish date deleted (
11/18/2020)
- Finish date deleted (
-
updated by
Max Mutzge on 11/26/2020 06:36 PM -
Comment added
Hi Harald,
unfortunately I couldn't reproduce this bug report with the provided information. For me it looks like this ...
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:24 PM - Votes changed from 2 to 3
-
updated by
Max Mutzge on 11/26/2020 06:23 PM - Version set to Wish List
-
updated by
Max Mutzge on 11/26/2020 06:23 PM -
Comment added
Hi Benjamin,
Thank you for the feature request. I added it to the wish list and we will prioritize it against the other ...
- Version set to Wish List
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Sander Kleijwegt on 11/26/2020 06:22 PM -
Comment added
user#67841
Yes, he custom field is added to the forms of all three work package types I have.
And yes, it is enabled gl...
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:21 PM -
Comment added
Hi Benjamin,
Thank you for the feature request. I added it to the wish list and we will prioritize it against the other ...
- Version set to Wish List
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:17 PM - The changes were retracted.
-
updated by
Max Mutzge on 11/26/2020 06:16 PM - Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/26/2020 06:14 PM -
Comment added
Hi Frank,
Thank you for the feature request. I added it to the wish list and we will prioritize it against the other fea...
- Version set to Wish List
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:07 PM -
Comment added
Hi Sander,
have you added the custom field to a work package form (https://docs.openproject.org/system-admin-guide/mana...
- Status changed from new to needs clarification
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 06:03 PM -
Comment added
Hi Nektarios,
Thank you for the feature request. I added it to the wish list and we will prioritize it against the other...
- Subject changed from Meetings log time to Log time automatically for meeting participants
- Version set to Wish List
- Requires doc change changed from No to Yes
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 05:57 PM -
Comment added
Confirmed in cloud:
Actual behavior:
details view: when I close it there's no abnormality, but when re-opening the wo...
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 05:46 PM -
Comment added
I added a vote to OP-5665 and will reject this feature request here, as it seems to be a duplicate thereof.
- Status changed from new to rejected
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 05:44 PM -
Comment added
+1 from OP-7883
- Votes changed from 10 to 11
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 05:42 PM - The changes were retracted.
-
updated by
Samantha Machon on 11/26/2020 04:37 PM - Votes set to 1
-
updated by
Frank Schmid on 11/26/2020 04:10 PM -
Comment added
+1
-
Comment added
-
updated by
Robin Wagner on 11/26/2020 03:45 PM - Subject changed from Apply grouping to XLS export to Apply grouping to XLS export for time and costs
-
updated by
Aleix Suau on 11/26/2020 01:04 PM - Description changed (Details)
-
updated by
Jens Ulferts on 11/26/2020 12:36 PM - Version changed from 11.0.4 to 11.1.0
-
updated by
Benjamin Bädorf on 11/26/2020 12:16 PM - Description changed (Details)
-
created by
Aleksei Baranov on 11/26/2020 12:12 PM -
updated by
Robin Wagner on 11/26/2020 11:36 AM - Finish date set to 12/01/2020
- Start date set to 12/01/2020
-
updated by
Robin Wagner on 11/26/2020 11:35 AM - Finish date set to 12/03/2020
- Start date set to 12/03/2020
-
updated by
Robin Wagner on 11/26/2020 11:35 AM - Finish date set to 12/01/2020
- Start date set to 12/01/2020
-
updated by
Robin Wagner on 11/26/2020 11:35 AM - Subject changed from Release communicated: newsletter, social media, heise, and more to Release communicated: social media
- Finish date set to 12/03/2020
- Start date set to 12/03/2020
-
updated by
Max Mutzge on 11/26/2020 11:19 AM -
Comment added
The related feature request is OP-7970
- Status changed from new to confirmed
-
Comment added
-
updated by
Max Mutzge on 11/26/2020 11:16 AM - Type set to Feature
- Project set to OpenProject
- Subject set to Consistent behaviour in project settings according to permissions of my role
- Description set (Details)
- Status set to new
- Priority set to Medium
- Author set to Max Mutzge
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- Requires doc change set to Yes
-
updated by
Benjamin Bädorf on 11/26/2020 11:11 AM - Description changed (Details)
- File 20201126_11h09m19s_grim.png added as attachment
-
updated by
Max Mutzge on 11/26/2020 11:03 AM - Description changed (Details)
- Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/26/2020 10:57 AM - Type set to Feature
- Project set to OpenProject
- Subject set to Check or un-check permissions automatically in "Roles and Permissions" settings when choosing certain permissions
- Description set (Details)
- Status set to new
- Priority set to Medium
- Author set to Max Mutzge
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- File image.png added as attachment
- Requires doc change set to No
-
updated by
Jens Ulferts on 11/26/2020 10:49 AM - Status changed from needs review to merged
-
updated by
GitHub on 11/26/2020 10:49 AM -
Comment added
PR Merged: Pull request 8856 Fix/copy budgets for opf/openproject has been merged by ulferts.
-
Comment added
-
updated by
Jens Ulferts on 11/26/2020 10:29 AM - Description changed (Details)
-
updated by
Birthe Lindenthal on 11/26/2020 10:23 AM - Status changed from in development to in specification
- File Glossar_OpenProject_deutsch.docx added as attachment
- File Glossary_OpenProject_english.docx added as attachment
-
updated by
Aleix Suau on 11/26/2020 10:22 AM - Description changed (Details)
-
updated by
Max Mutzge on 11/26/2020 10:10 AM - Type set to Bug
- Project set to OpenProject
- Subject set to Option to set available work package types in project settings visible for users not allowed to edit them
- Description set (Details)
- Status set to new
- Priority set to Medium
- Author set to Max Mutzge
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- File image.png added as attachment
- File image.png added as attachment
- File image.png added as attachment
- File image.png added as attachment
- File image.png added as attachment
- Requires doc change set to No
-
updated by
Jens Ulferts on 11/26/2020 08:36 AM -
Comment added
Thanks for bringing it to our attention, Frank. We'll take a look at it.
- Status changed from new to confirmed
-
Comment added
11/25/2020
-
updated by
Niels Lindenthal on 11/25/2020 09:03 PM - Version set to 11.1.0
- Requires doc change changed from No to Yes
-
created by
Niels Lindenthal on 11/25/2020 09:02 PM -
updated by
Niels Lindenthal on 11/25/2020 08:57 PM -
Comment added
Hi Jens Ulferts,
good idea let's change the icon to the gear and the text to Configure. I will open a new work package f...
-
Comment added
-
updated by
Robin Wagner on 11/25/2020 06:15 PM - Reach set to 1.5 = Small reach (~5% to ~25%)
-
updated by
Robin Wagner on 11/25/2020 06:14 PM - Reach set to 6.0 = Impacts a large percentage (~50% to ~80%)
-
updated by
Robin Wagner on 11/25/2020 06:13 PM - Reach set to 1.5 = Small reach (~5% to ~25%)
-
updated by
Robin Wagner on 11/25/2020 06:12 PM - Reach set to 0.5 = Minimal reach (Less than ~5%)
-
updated by
Robin Wagner on 11/25/2020 06:11 PM -
Comment added
Reach set to "minimal" as few users are using forums on their OpenProject environments.
- Reach set to 0.5 = Minimal reach (Less than ~5%)
-
Comment added
-
updated by
Robin Wagner on 11/25/2020 06:10 PM - Reach set to 1.5 = Small reach (~5% to ~25%)
-
updated by
Robin Wagner on 11/25/2020 06:09 PM - Reach set to 0.5 = Minimal reach (Less than ~5%)
-
updated by
Robin Wagner on 11/25/2020 05:34 PM -
Comment added
+1 from Enterprise customer
- Votes changed from 1 to 2
-
Comment added
-
updated by
Robin Wagner on 11/25/2020 05:33 PM -
Comment added
+1 from Enterprise customer
- Votes changed from 12 to 13
-
Comment added
-
updated by
Robin Wagner on 11/25/2020 05:32 PM -
Comment added
+1 from Enterprise customer
- Votes changed from 6 to 8
-
Comment added
-
created by
Frank Schmid on 11/25/2020 04:56 PM -
updated by
Jens Ulferts on 11/25/2020 04:50 PM -
Comment added
This is still on hold and questions need to be answered. As such, it will not be completed in 11.0.4. I am thus moving i...
- Version deleted (
11.0.4)
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 04:11 PM -
Comment added
Fixed in https://github.com/opf/openproject/commit/e111794528778f08fa3b307de5cf4c00ff809410
- Status changed from confirmed to merged
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 03:44 PM - Subject changed from Create release branch release/X.X to Create release branch release/11.1
-
updated by
Jens Ulferts on 11/25/2020 03:43 PM - Finish date set to 11/30/2020
- Start date set to 11/30/2020
-
updated by
Jens Ulferts on 11/25/2020 03:31 PM - Version changed from 11.0.4 to 11.1.0
-
updated by
Jens Ulferts on 11/25/2020 03:31 PM - Version set to 11.0.4
-
updated by
Jens Ulferts on 11/25/2020 03:29 PM - Status changed from in development to on hold
- Version deleted (
11.0.4)
-
updated by
Jens Ulferts on 11/25/2020 03:29 PM - Version deleted (
11.0.4)
- Version deleted (
-
updated by
Jens Ulferts on 11/25/2020 03:29 PM - Version deleted (
11.0.4)
- Version deleted (
-
updated by
Jens Ulferts on 11/25/2020 03:28 PM - Priority changed from Medium to High
- Version deleted (
11.0.4)
-
updated by
Jens Ulferts on 11/25/2020 03:28 PM - Version deleted (
11.0.4)
- Version deleted (
-
updated by
Robin Wagner on 11/25/2020 03:02 PM - The changes were retracted.
-
updated by
Robin Wagner on 11/25/2020 02:58 PM - The changes were retracted.
-
updated by
Robin Wagner on 11/25/2020 02:58 PM - The changes were retracted.
-
created by
Robin Wagner on 11/25/2020 02:47 PM -
updated by
Robin Wagner on 11/25/2020 01:56 PM -
Comment added
Reach: Significant (significant number of users use XLS export)
Impact: Normal (annoying but not a critical issue)
Confi...
- Reach set to 1.5 = Small reach (~5% to ~25%)
-
Comment added
-
created by
Aleksei Baranov on 11/25/2020 01:44 PM -
updated by
Robin Wagner on 11/25/2020 01:44 PM -
Comment added
+1 from Enterprise customer
- Votes set to 2
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 01:30 PM -
Comment added
I would not like to mix it into the work package autocompleter rehaul task as it is already large enough as it is.
Howev...
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 01:28 PM -
Comment added
Thanks, that is fine for me.
Jens Ulferts adding you as watcher to this topic. When planning for the autocompletion reha...
-
Comment added
-
updated by
Aleix Suau on 11/25/2020 01:26 PM - Assignee set to Aleix Suau
-
updated by
Wieland Lindenthal on 11/25/2020 01:20 PM -
Comment added
Niels Lindenthal I believe "less than a week" could be correct. Or do you need it more specific? As discussed with Jens ...
-
Comment added
-
updated by
Aleix Suau on 11/25/2020 01:11 PM - Description changed (Details)
-
updated by
Wieland Lindenthal on 11/25/2020 01:10 PM -
Comment added
I extracted the missing use case to OP-7963 and close this WP here.
- Status changed from needs review to closed
-
Comment added
-
updated by
Wieland Lindenthal on 11/25/2020 01:09 PM - Type set to Feature
- Project set to OpenProject
- Subject set to Global search across multiple WP attributes
- Description set (Details)
- Status set to new
- Priority set to Low
- Version set to Wish List
- Author set to Wieland Lindenthal
- % Complete set to 0%
- Scheduling mode set to Automatic
- Working days set to include non-working days
- Reach set to 6.0 = Impacts a large percentage (~50% to ~80%)
- Requires doc change set to No
- RICE Score set to 1.5
-
updated by
Wieland Lindenthal on 11/25/2020 12:45 PM -
Comment added
I don't remember anymore. I reject it.
- Status changed from new to rejected
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 12:44 PM -
Comment added
Hi Samantha Machon do you know whether the work package has parent (or even more ancestors) or children (or even more de...
-
Comment added
-
updated by
Robin Wagner on 11/25/2020 11:58 AM - Assignee set to Robin Wagner
-
updated by
GitHub on 11/25/2020 11:47 AM -
Comment added
PR Opened: Pull request 8859 Export Gantt as PDF for opf/openproject has been opened by TheGr8Nik.
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 11:30 AM - Status changed from new to specified
- Version changed from Wish List to Product Backlog
- RICE Score set to 4
- Reach set to 6.0 = Impacts a large percentage (~50% to ~80%)
-
updated by
Samantha Machon on 11/25/2020 10:34 AM -
Comment added
+1 from customer who would like to create multiple default views
- Votes changed from 11 to 12
-
Comment added
-
updated by
Samantha Machon on 11/25/2020 10:19 AM -
Comment added
Hi Jens Ulferts , Thank you for checking the issue. The customer provided some more information:
1.Create work package ...
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 09:36 AM - Status changed from in specification to specified
-
updated by
Jens Ulferts on 11/25/2020 09:34 AM -
Comment added
Replaced in favor of #33242
- Status changed from new to rejected
- Parent deleted ()
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 09:31 AM -
Comment added
Hi Elio Qoshi,
can you please have a look at this?
Jens suggest to have the "Group by"-option to be toggled. What do you...
- Status changed from new to in specification
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 09:28 AM -
Comment added
Hi Jens Ulferts,
can you please add more information to this so we can add it to the Product Backlog?
Thanks
Niels
- Assignee set to Jens Ulferts
- Version set to Wish List
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 09:24 AM -
Comment added
Hi Jens Ulferts,
Thanks for your opinion. I agree. Can we set the status to "specified"?
Best
Niels
-
Comment added
-
updated by
Niels Lindenthal on 11/25/2020 09:20 AM -
Comment added
Hi Jens Ulferts,
I agree. If we add more attributes to the cards we need to allow for more configuration.
Best
Niels
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 09:06 AM -
Comment added
Niels Lindenthal , I think that the confidence is way lower. I for one would not want to have the date on the boards. E....
- RICE Score changed from 12 to 3
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 09:01 AM -
Comment added
Niels Lindenthal Estimates are ok. As to me liking the feature: Meh, it is ok as it would at least reduce the amount of ...
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 08:57 AM -
Comment added
The solution IMO would be to still display the "Group by" option and allow for it to be toggled.
The estimate is ok eit...
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 08:55 AM -
Comment added
Niels Lindenthal I think that there are too many uncertainties in here that need to be clarified before it can be estima...
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 08:52 AM -
Comment added
The estimate is still valid
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 08:51 AM -
Comment added
I think this can be closed. While not having a dedicated, readymade widget, using the generic "Work package table" widge...
- Status changed from specified to closed
-
Comment added
-
updated by
Jens Ulferts on 11/25/2020 08:49 AM -
Comment added
I second the estimates.
-
Comment added
-
created by
Jens Ulferts on 11/25/2020 08:47 AM -
updated by
Ben Newman on 11/25/2020 04:07 AM -
Comment added
Oh sorry, I did not see your comment before now.
Yes, that is exactly what I want I just did not see it before.
-
Comment added
-
updated by
Ben Newman on 11/25/2020 03:57 AM -
Comment added
I can not believe this is moved back to the Wishlist.
This is a basic feature that Every project management software I ...
-
Comment added
-
updated by
Ben Newman on 11/25/2020 03:55 AM -
Comment added
How is this supposed to be evaluated on a Rice Score if it has no Rice Score?
-
Comment added
-
updated by
Max Mutzge on 11/25/2020 02:50 AM -
Comment added
Confirmed: Second admin has admin role, the box "users can be deleted by admins" is ticked.
Deleting the second admin wo...
- Description changed (Details)
- Status changed from new to confirmed
-
Comment added
-
updated by
Max Mutzge on 11/25/2020 02:38 AM - Requires doc change set to Yes
-
updated by
Max Mutzge on 11/25/2020 02:38 AM - Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/25/2020 02:38 AM - Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/25/2020 02:37 AM - Requires doc change changed from No to Yes
-
updated by
Max Mutzge on 11/25/2020 02:29 AM - Requires doc change changed from No to Yes