Performance implementation (BAC/ACWP/EV/CPI/ETC/EAC)

Hello, I was wondering if there is the possibility to implement Performance columns at the Projects (EVMS)

BAC = ESTIMATED TIME (OK!)

ACWP = SPENT TIME (OK!)

PROGRESS (OK!)

EV (EARNED VALUE) = BAC * PROGRESS (NOK!) --> This is the standard time at 100% performance

CPI (COST PERFORMANCE INDEX)= EV / ACWP (NOK!) - % --> This is the performance itself

ETC (ESTIMATED TIME TO COMPLETE) = (BAC - EV) / CPI --> Using the performance indicator, the estimate time to complete the WP

EAC (ESTIMATE AT COMPLETION) = ACWP + ETC --> Using a relation between performance, the final hours

Regards, :)

Message actions

is there any updates for this issue? I think this is a good feature to add.