Content
Performance implementation (BAC/ACWP/EV/CPI/ETC/EAC)
Started January 30, 2019 14:56 · 1 reply · 2 participants
Hello, I was wondering if there is the possibility to implement Performance columns at the Projects (EVMS)
BAC = ESTIMATED TIME (OK!)
ACWP = SPENT TIME (OK!)
PROGRESS (OK!)
EV (EARNED VALUE) = BAC * PROGRESS (NOK!) --> This is the standard time at 100% performance
CPI (COST PERFORMANCE INDEX)= EV / ACWP (NOK!) - % --> This is the performance itself
ETC (ESTIMATED TIME TO COMPLETE) = (BAC - EV) / CPI --> Using the performance indicator, the estimate time to complete the WP
EAC (ESTIMATE AT COMPLETION) = ACWP + ETC --> Using a relation between performance, the final hours
Regards, :)
is there any updates for this issue? I think this is a good feature to add.