**As a** project manager
**I want to** be able to maintain manual scheduling mode when adding a work package as a successor
**So that** I don't lose the dates when I add it as a successor.
#### Acceptance criteria
##### General
* If a work package was previously manually scheduled, but is then added as a successor. Or if a predecessor is added to a manually scheduled work package:
* We will give the user a confirmation dialog with two options (see mockups for text):
* Maintain manual scheduling
* Switch to automatic
* This affects Gantt chart and the WP view
#### Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
**Options when adding a predecessor to a manually scheduled work package in Gantt view:**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226792/content">
**I want to** be able to maintain manual scheduling mode when adding a work package as a successor
**So that** I don't lose the dates when I add it as a successor.
#### Acceptance criteria
##### General
* If a work package was previously manually scheduled, but is then added as a successor. Or if a predecessor is added to a manually scheduled work package:
* We will give the user a confirmation dialog with two options (see mockups for text):
* Maintain manual scheduling
* Switch to automatic
* This affects Gantt chart and the WP view
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
**Options when adding a predecessor to a manually scheduled work package in Gantt view:**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226792/content">