Content
Roadmap
OpenProject - Product Backlog
133 closed (26%) 371 open (74%)
Related work packages
- Feature SPAR-111: Add dialog when linking a manually scheduled work package as successor
- Feature SPAR-112: Add dialog when successor must switch to manual mode to preserve its dates
- Feature SPAR-150: Relations tab: Auto-scroll to a newly-created child
wih
There are currently no work packages assigned to this version.
OpenProject - Wish List
304 closed (11%) 2416 open (89%)
Related work packages
- Epic SPAR-2: Critical path
- Epic SPAR-5: Schedule from the project start date/project finish date (backwards planning)
- Feature SPAR-3: Adding new columns for relations
- Feature SPAR-4: Show child work packages from other projects in work package view
- Feature SPAR-6: Sum spent time on working package view for all and for subgroups
- Feature SPAR-7: Inherited Attributes for New Children
- Feature SPAR-8: Enable manual scheduling of parent work packages directly from within Gantt chart
- Feature SPAR-9: Enter and show Estimated time in days
- Feature SPAR-10: Template or copy a task cluster with all relations
- Feature SPAR-11: Do not set relation to original work package when copying work package
- Feature SPAR-12: Follower work package should start earlier if the predecessor finished prematurely
- Feature SPAR-13: Bulk edit to unset start/finish date
- Feature SPAR-16: Filter option is not available in Child tickets
- Feature SPAR-17: Feature/Epic Links in User Story Cards
- Feature SPAR-18: Cross Team dependencies shown in user stories
- Feature SPAR-20: Work package "Done ratio" calculation of parent work package
- Feature SPAR-24: Disable following work packages from automatically deriving dates when preceding one is moved
- Feature SPAR-25: Expand task relations for URL and WiKi pages
- Feature SPAR-26: Ansicht in Untergeordnete Arbeitspakete anpassen. Support Anfrage (#3229) (#3241)
- Feature SPAR-27: Follows / Precedes relationship adds unneccesary days to work packages
- Feature SPAR-29: Allow parent and children to be in "blocks/blocked by" relationship
- Feature SPAR-30: Specify relation type in journalised activity entries for dates changes caused by relations
- Feature SPAR-62: Show reported values for work and remainig work and % complete in the versions detail page
- Feature SPAR-66: Project-level setting for % Complete calculation mode
- Feature SPAR-75: Remove work and progress estimates from type Milestone
- Feature SPAR-76: Progress: Clicking on "% Complete" displays the Progress and Work estimates and progress pop-over
- Feature SPAR-77: Add Work, Remaining work and % complete to baseline comparison
- Feature SPAR-82: Enable/Disable "Progress calculation" at a project-level
- Feature SPAR-95: Primerised version overview page with progress indicators
- Feature SPAR-103: Allow "Start as soon as possible" to align with project or stage start dates
- Feature SPAR-152: Date picker: when a user manually enters a non-working day (and working days only is on), show an inline error message
- Feature SPAR-159: Direct and indirect relations (successors/predecessors)
- Feature SPAR-257: Make it possible to include or exclude working days when defining lag per relation
- Feature SPAR-275: Add an admin setting to turn off Automatic scheduling mode
- Feature SPAR-279: Set a maximum duration for work packages