Reported work packages: 1
06/12/2014
-
updated on 06/12/2014 11:50 AM
-
Comment added
This was solved by changing a setting in Admin module.
Thank you.
- Status changed from new to closed
-
Comment added
-
created on 06/12/2014 11:49 AMHi Niels,
Thank you. You nailed it.
That solved my problem.
-Sam -
updated on 06/12/2014 11:49 AMHi,
I am facing a peculier issue. When I created a milestone it was not allowing me to select the due date anything othe...- The changes were retracted.
-
created on 06/12/2014 09:24 AMThomas Klahr wrote:
8<—-snip
btw, I understand a Milestone differently. Its an indicator of my project completion.
Fo... -
updated on 06/12/2014 09:24 AMHi,
I am facing a peculier issue. When I created a milestone it was not allowing me to select the due date anything othe...- The changes were retracted.
-
created on 06/12/2014 09:23 AMThank you for reply Tom.
No, even if I select a new work package and select type as “Phase”, I get same error:
Due date ...
06/11/2014
-
created on 06/11/2014 09:12 AM
-
created on 06/11/2014 08:44 AMHi,
To associate mysql database to openproject, you don’t need ssh provided your host have requried gem installed alread... -
General discussion: Install on host (Project: OpenProject)updated on 06/11/2014 08:44 AMI just want to make sure my research is correct.
I wanted to install openproject on my shared hosting. Which from what i...- The changes were retracted.
-
created on 06/11/2014 08:39 AMHi,
I am facing a peculier issue. When I created a milestone it was not allowing me to select the due date anything othe... -
created on 06/11/2014 08:25 AMIn config/environments/production.rb, when I disabled line
config.assets.digest = true
everything worked.
Thank you.
Reg... -
updated on 06/11/2014 08:25 AMHi,
I installed openproject with multi-user environment. It renders with some javascript problems using builtin server b...- The changes were retracted.