Due date cannot be set to future date
Added by Sameer I over 10 years ago
Hi,
I am facing a peculier issue. When I created a milestone it was not allowing me to select the due date anything other than start date. If I try to do so, OP throws following error:
Due date is not on start date, although this is required for milestones
Is this a bug in OperProject version 3.0.3?
-Sam
Replies (5)
Hi Sam,
this is not a bug but a feature.
Like in every project planning system I know a milestone ist a one-day event.
Maybe you use a project phase?
Greetings Tom
Thank you for reply Tom.
No, even if I select a new work package and select type as “Phase”, I get same error:
Due date is not on start date, although this is required for milestones
Regards,
-Sam
Thomas Klahr wrote:
8<—-snip
btw, I understand a Milestone differently. Its an indicator of my project completion.
For example, Phase 1 of my project may define 5 milestones, each requiring different effort (in terms of PDs).
Each milestone may have multiple work items. Total time estimated to complete all work items in a milestone is the total time taken to reach a particular milestone. For reporting purpose, say, how much of the work is done for a particular milestone, it is important to have this kind of setup.
It can be different from the way you look at it. In any case even selecting the work package type as Task throws same error.
-Sam.
Sameer I wrote:
Hi Sam,
Each type (Phase, Milestone, Bug, Task etc.) has several settings. One of these settings is “mark type as milestone”. If this setting is enabled both dates need to be the same.
You can check the settings in Modules -> Administration -> Types -> “Type”.
Regards
Niels
Hi Niels,
Thank you. You nailed it.
That solved my problem.
-Sam