Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Timelines Problems

Timelines Problems

Added by James Jones about 11 years ago

I’m having some problems with timelines. Hoping someone on this forum can shed some light. Any help would me much appreciated.

Firstly, whenever I add a column to any timeline such as status or start dates, an extra column is added with the heading ‘translation missing: timelines.filter.column.’. I’m not sure what exactly is causing this.

Secondly I’m having trouble getting the timelines of sub-projects showing up in the parent project timeline. In the parent project timeline options I’ve set ‘show subprojects of’ to the parent project in the ‘Filter Projects’ section. I can’t find any documentation about this stuff.

I’ve attached a screenshot that shows both these problems in action.


Replies (5)

RE: Timelines Problems - Added by James Jones about 11 years ago

Well just to update, we upgraded open project to 3.0 stable whereas we were running the beta beforehand. This fixed the problem of the extra column with ‘translation missing: timeline.filter.column’.

Still not sure how timelines interact with projects and subprojects though. Any pointers would be appreciated.

RE: Timelines Problems - Added by James Jones about 11 years ago

Okay another update. I managed to get sub projects timelines showing up in the parent project by setting up ‘status reportings’. So a win there. I’m a bit saddened by the complete lack of response here. If there’s no documentation and no support you leave a lot of beginners out of the loop.

RE: Timelines Problems - Added by Stephane Fournier about 11 years ago

Hello James

I use version 3.1.0pre1 and I have the extra column with ‘translation missing: timeline.filter.column’ problem. Can you tell me what did to solve it?

Thanks.

RE: Timelines Problems - Added by Khaoula E. about 11 years ago

Hello James,

I want to ask about the ‘status reporting’. Even if I related the sub-projects, it only showed the titles without the work packages. Only when you click does it show the sub-projects’ timelines. Is this how it is shown to you?

Thank you!

-Khaoula

RE: Timelines Problems - Added by James Jones almost 11 years ago

Sorry for such a late reply. I was clearing out emails and saw these responses.

@Stephane Fournier

I actually find that error comes up again when you edit the timeline report. It seems you have to create a new timeline report to avoid this error.

@Khaoula E.

I found that I had to go into ‘Dependencies’ on the main left side menu and set up new dependencies between sub-project and the parent project. It only works one way but right now I can’t remember whether you set it up within the parent project, or the sub-project. Hope that helps a bit.

  • (1 - 5/5)