Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Flexible/Reactive Scheduling - Timelines

Flexible/Reactive Scheduling - Timelines

Added by Kendell Welch over 9 years ago

Hello,

I had some trouble making sure that I was on the very newest version, but I got that resolved yesterday. So…here’s what I really want to ask:

In my department, we have something like 50 “Projects” with various “Work Orders” associated. We have to give monthly updates to both our users and upper management on progress and estimates of completion. Our IT department really likes the Timeline feature in OpenProject, however, it requires us to provide hard dates for Work Orders. That is not possible for us, as we are also a responsive team.

Obviously we can set priority levels for stuff, and that works fine. But, it would be much better if we could assign an “estimated hours for completion” or something like that, based on the priorities and scheduled availability of our team, rather than providing hard dates, and thus the timeline would self-adjust for reporting purposes.

I’m not sure if this is possible now and I just haven’t figured out how to do it, or if I should make it a feature request. I would appreciate any input!

Thanks!
Kendell


Replies (1)

RE: Flexible/Reactive Scheduling - Timelines - Added by Robin Wagner over 9 years ago

Hello Kendell,

thanks for your message.
The feature you describe does not yet exist in OpenProject. It is possible to set the “Estimated time” for work packages.
However, this information is not used or displayed on the timeline.

Feel free to open a feature request (User Story) in the Wish list

Best,
Robin