Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Not possible to show work packages from subproject in main Timeline Project

Not possible to show work packages from subproject in main Timeline Project

Added by Karol Skolar about 11 years ago

Hi there,
I already install and configure OpenProject and now discovering features.
I’m just surprised, that I am not able to show in the timeline of the main project workpackages from SubProjects. Its not necessary to have Timeline modules in every subproject.
Is is possible to configure this somehow or its against the philosophy of OP?
Thanks!

Karol


Replies (5)

RE: Not possible to show work packages from subproject in main Timeline Project - Added by Birthe Lindenthal about 11 years ago

Hi Karol,

yes, it’s possible. You have to consider two precondition:

  1. You have to be member of the respective project and subproject.
  2. You have to create a reporting relation within the subproject to the project you want to report in:
    Go to -> Status reportings -> add the respective project where you want to display the information

RE: Not possible to show work packages from subproject in main Timeline Project - Added by Karol Skolar about 11 years ago

Thanks Birthe!
I was configuring reporting relationship in opposite way, just did not read carefully captions :(.
Sorry, and thanks again.

Karol

Birthe Lindenthal wrote:

Hi Karol,

yes, it’s possible. You have to consider two precondition:

  1. You have to be member of the respective project and subproject.
  2. You have to create a reporting relation within the subproject to the project you want to report in:
    Go to -> Status reportings -> add the respective project where you want to display the information

RE: Not possible to show work packages from subproject in main Timeline Project - Added by Karol Skolar about 11 years ago

Birthe please,
is it possible to show created Meeting from Meeting Plugin in Timeline or in Calendar?
Thanks.

Karol

Karol Skolar wrote:

Thanks Birthe!
I was configuring reporting relationship in opposite way, just did not read carefully captions :(.
Sorry, and thanks again.

Karol

Birthe Lindenthal wrote:

Hi Karol,

yes, it’s possible. You have to consider two precondition:

# You have to be member of the respective project and subproject.
# You have to create a reporting relation within the subproject to the project you want to report in:
Go to -> Status reportings -> add the respective project where you want to display the information

RE: Not possible to show work packages from subproject in main Timeline Project - Added by Birthe Lindenthal about 11 years ago

Hi Karol,

this is not possible yet. I think this is a valuable feature, I have created a new user story for this requirement:
https://www.openproject.org/work_packages/4742

Best
Birthe

RE: Not possible to show work packages from subproject in main Timeline Project - Added by Karol Skolar about 11 years ago

Thanks Birthe!

Karol

Birthe Lindenthal wrote:

Hi Karol,

this is not possible yet. I think this is a valuable feature, I have created a new user story for this requirement:
https://www.openproject.org/work_packages/4742

Best
Birthe