Added by Zorin Wiseputra about 10 years ago
I wonder if if Issues and their duration will appear in Calendar or Timeline. That will be appeasing isn’t it?
Hi Zorin,
yes, work packages appear in both the calendar and the timelines by default. You can however apply filters in both the calendar the timelines to customize exactly which types of work packages should be shown.
Best, Robin
Replies (1)
Hi Zorin,
yes, work packages appear in both the calendar and the timelines by default.
You can however apply filters in both the calendar the timelines to customize exactly which types of work packages should be shown.
Best,
Robin