Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Milestone as fixed endpoint

Milestone as fixed endpoint

Added by Nico Spengler 8 months ago

Hi,

is there any way to set a milestone as a fixed date which can not be moved and no work package can be planned longer than this date?


Replies (3)

RE: Milestone as fixed endpoint - Added by Alexander Stock 7 months ago

Hi Nico,

great question! Currently, a milestone can be moved by every user with the right permissions. It is possible to select a manual scheduling mode for a milestone (and all other work package types) though. When enabled, this mode prevents an automatic moving of the milestone when preceding work packages take longer than initially planned. At the same time, however, this allows preceding work packages to be planned longer than the milestone itself.

Please find here more information on manual and automatic scheduling:
https://www.openproject.org/docs/user-guide/gantt-chart/scheduling/#automatic-and-manual-scheduling-modes

I encourage you to submit a feature request with your user story and acceptance criteria so we can add it to the wish list -> https://www.openproject.org/docs/development/submit-feature-idea/#submit-a-feature-idea

Best,

Alexander

RE: Milestone as fixed endpoint - Added by Harold Maxwell 21 days ago

Hi Nico,

great question! Currently, a milestone can be moved by every user with the right permissions. It is possible to select a manual scheduling mode for a milestone (and all other work package types) though. When enabled, this mode prevents an automatic moving of the milestone when preceding work packages take longer than initially planned. At the same time, however, this allows preceding work packages to be planned longer than the milestone itself.

Please find here more information on manual and automatic scheduling:
https://www.openproject.org/docs/user-guide/gantt-chart/scheduling/#automatic-and-manual-scheduling-modes

I encourage you to submit a feature request with your user story and acceptance criteria so we can add it to the wish list -> https://www.openproject.org/docs/development/submit-feature-idea/#submit-a-feature-idea Curve Rush

Best,

Alexander

Thanks for your help. It is very helpful.

RE: RE: Milestone as fixed endpoint - Added by Christophe GESCHÉ 21 days ago

It's just a figment of the imagination, but this request makes me think more of a "named date" than a dated milestone.

That is, the ability to give a "name to a date," a name that can be edited, but not the date.

And what goes with it is the idea of ​​being able to give this date properties, in addition to this name.