Content
Dependencies do not consider time
Added by peacecop kalmer: piiskop almost 2 years ago
i created two tasks, both for the same date, the second one depending on the first one. The system moved the second task to the next date although showed the initial date after moving in the details. This is incorrect behavior. Multiple tasks can be performed on a same day whereas an input for a task can come as an output of another task of the same date. Why is there no time field so that i could set start and end time for each task? Why are meetings not included in calendars? Currently, i have to double the work as meetings can have time values but they cannot be included in calendars and if i want to log time for people who did participate in a meeting, i need to create a task for that meeting.