Hello
In the settings I have a lot of different status:
Unfortunately, these status are not used in the project tasks:
Do you have any idea on what I've missed ?
Thank you
The status values used are depending on the WP-Type and how you define their workflow:
oh! OK I understand. But when I create a new Status, I can't select a type to assign:
It's the other way around:
(It's a lot of work when configuring OP in the beginning)
Replies (3)
The status values used are depending on the WP-Type and how you define their workflow:
oh! OK I understand. But when I create a new Status, I can't select a type to assign:
It's the other way around:
(It's a lot of work when configuring OP in the beginning)