Content
Roadmap
OpenProject - Product Backlog
102 closed (29%) 244 open (71%)
Related work packages
- Feature #58421: Allow "Start as soon as possible" to align with project or stage start dates
- Feature #59542: Add dialog when linking a manually scheduled work package as successor
- Feature #59731: Add dialog when successor must switch to manual mode to preserve its dates
- Feature #61143: Relations tab: Auto-scroll to a newly-created child
- Feature #63460: Make it possible to include or exclude working days when defining lag per relation
- Feature #67002: Set a maximum duration for work packages
wih
There are currently no work packages assigned to this version.
OpenProject - Wish List
312 closed (11%) 2427 open (89%)
Related work packages
- Epic #26231: Critical path
- Epic #30701: Schedule from the project start date/project finish date (backwards planning)
- Feature #28637: Adding new columns for relations
- Feature #29814: Show child work packages from other projects in work package view
- Feature #31307: Inherit properties of parent work packages for child
- Feature #31998: Sum spent time on working package view for all and for subgroups
- Feature #33389: Inherited Attributes for New Children
- Feature #34706: Enable manual scheduling of parent work packages directly from within Gantt chart
- Feature #35027: Enter and show Estimated time in days
- Feature #35613: Template or copy a task cluster with all relations
- Feature #35746: Do not set relation to original work package when copying work package
- Feature #35749: Follower work package should start earlier if the predecessor finished prematurely
- Feature #36252: Bulk edit to unset start/finish date
- Feature #36748: Filter option is not available in Child tickets
- Feature #37579: Feature/Epic Links in User Story Cards
- Feature #37580: Cross Team dependencies shown in user stories
- Feature #40166: Work package "Done ratio" calculation of parent work package
- Feature #44164: Disable following work packages from automatically deriving dates when preceding one is moved
- Feature #44287: Expand task relations for URL and WiKi pages
- Feature #45477: Ansicht in Untergeordnete Arbeitspakete anpassen. Support Anfrage (#3229) (#3241)
- Feature #45981: Follows / Precedes relationship adds unneccesary days to work packages
- Feature #48621: Allow parent and children to be in "blocks/blocked by" relationship
- Feature #49407: Specify relation type in journalised activity entries for dates changes caused by relations
- Feature #52186: Show reported values for work and remainig work and % complete in the versions detail page
- Feature #52737: Project-level setting for % Complete calculation mode
- Feature #54511: Remove work and progress estimates from type Milestone
- Feature #54726: Progress: Clicking on "% Complete" displays the Progress and Work estimates and progress pop-over
- Feature #55348: Add Work, Remaining work and % complete to baseline comparison
- Feature #55804: Enable/Disable "Progress calculation" at a project-level
- Feature #57955: Primerised version overview page with progress indicators
- Feature #61434: Date picker: when a user manually enters a non-working day (and working days only is on), show an inline error message
- Feature #61529: Direct and indirect relations (successors/predecessors)
- Feature #66584: Add an admin setting to turn off Automatic scheduling mode