Content
Activity
11/13/2024
-
updated by
Marc Alcobé on 11/13/2024 11:26 AM -
Comment added
Niels Lindenthal,
The Figma link has been updated with the latest decisions taken in our meeting.
Best,
Marc
-
Comment added
-
updated by
Marc Alcobé on 11/13/2024 10:24 AM -
Comment added
Hi Niels Lindenthal,
Of course. What do you mean by showing the filter criteria?
Exporting the PDF depending on the f...
-
Comment added
11/12/2024
-
updated by
Niels Lindenthal on 11/12/2024 10:12 PM -
Comment added
Hi Marc Alcobé,
Can you please create a mockup showing the MVP scope without the overview table and showing the filter c...
- Description changed (Details)
- List deleted (
(deleted option))
-
Comment added
-
updated by
Parimal Satyal on 11/12/2024 03:50 PM -
Comment added
Added details concerning editing relations.
- Description changed (Details)
- File Edit_successor_-_Edit_lag.png added as attachment
- File Edit_successor_-_Edit_lag_and_description.png added as attachment
- File Edit_successor_-_Edit_lag_and_description.png added as attachment
-
Comment added
-
updated by
Niels Lindenthal on 11/12/2024 03:17 PM - Description changed (Details)
- Version changed from 15.2.0 to 15.1.0
-
updated by
Niels Lindenthal on 11/12/2024 12:25 PM - Work changed from 60d 0h to 90d 0h
- Remaining work changed from 60d 0h to 90d 0h
- Total work changed from 62d 0h to 92d 0h
- Total remaining work changed from 62d 0h to 92d 0h
- PD (min) changed from 50 to 60
- PD (max) deleted (
70)
-
updated by
Niels Lindenthal on 11/12/2024 12:24 PM - Work changed from 50d 0h to 75d 0h
- Remaining work changed from 50d 0h to 75d 0h
- Total work changed from 50d 0h to 75d 0h
- Total remaining work changed from 50d 0h to 75d 0h
- PD (max) deleted (
75)
11/11/2024
-
updated by
Bernard Gray on 11/11/2024 04:16 AM -
Comment added
Please note, this feature is blocking our upgrade path to 14.x.
Our small product planning team use it heavily (~195 pr...
-
Comment added
-
created by
Bernard Gray on 11/11/2024 02:30 AM
11/08/2024
-
updated by
Niels Lindenthal on 11/08/2024 03:50 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:50 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:50 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM -
Comment added
Updated automatically by changing values within child work package SPAR-6
- Working days set to working days only
-
Comment added
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - The changes were retracted.
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - The changes were retracted.
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - List changed from cProject, (deleted option) to cProject
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM - Parent deleted (
Additional calculation methods and advanced configuration options for project progress reporting)
- Parent deleted (
-
updated by
Niels Lindenthal on 11/08/2024 03:49 PM -
Comment added
Hi Jens Ulferts and Christophe Bliard,
I would like to scope this Epic to 2024. So I removed the following features:
...
-
Comment added
-
updated by
Niels Lindenthal on 11/08/2024 02:59 PM - Version changed from Wish List to 15.2.0
-
updated by
Aaron Contreras on 11/08/2024 02:14 PM -
Comment added
Todos before marking Pull request as ready:
Re-render relations tab counter on changes
Use special endpoint to list...
-
Comment added
Also available in: Atom