Hi,
I want to ask about reports in OpenProject.
We have a workpackage in a project, that multiple people can work with it. For example Work package A can have status Development and assingnee A. After assignee A completes the work package, will assignee it to assignee B and change its status to Test.
This can be seen in the history of the work package.
Is there a way to see which work packages an assignee was working on, lets say on 12/2015, even though that the work package status and assignee changed during this month?
And is there a way to create a report with this information?

Message actions

Hi Stelios,

it’s not possible to filter for work packages based on historical settings.
Only the current state of the work packages can be filtered for (and saved as a report).

Message actions

Hi Robin,
Thanks for your help!
Is it possilbe to extract it from the database with an SQL query?