Bug: Erroneous dates shown in Work Packages view

Hi Openproject Team,

There is an error when the dates are shown in Work Packages View.

When the task is entered you choose a date, let’s say 21-06-2015, but in Work Packages view it is shown as 20-06-2015.

See the attachment.

Thanks id avance.

My system:
Openproject CE 4.1
Ddebian 7 64 bits
Timezone: GMT-5 America/Guayaquil

Message actions

Hello Javier!

Thanks for the bug report! This might be an issue with using the correct timezone when displaying the dates. We will be looking into it for the upcoming 4.1.2 release.

Message actions

I have opened an internal bug report - there is also an open bug report (duplicate) available under https://community.openproject.org/work_packages/20210

Message actions

Javier, just a pointer that the bug will definitely be fixed in 4.1.2. Thanks again for reporting it.

Message actions

Hi Florian!

I’m very glad using Openproject. I have to say your proactivity is inspiring. I’ll be looking forward to the 4.1.2 patch.

Thanks again

Message actions

Hello Javier,

FYI: We released OpenProject 4.1.2 last Thursday.