[glitch] Hierarchy not correct in the work packages list displayed from the context menu of the sprint backlog

There is something wrong with the work packages list displayed from the context menu of the sprint backlog.
Example: task A and task B are children of Richiesta 1 (user story).
On the list only task A is displayed as child.
See glitch2a.jpg.

glitch2a.jpg

The same list from work packages left menu are displayed correctly.
See glitch2b.jpg.

glitch2b.jpg

Open Project Community Edition 4.0.5 over Ubuntu 14.04 server.
Windows 7 64bit, dpi 150%, firefox 34.0.5 (the latest version available).