Assign single task to multiple members
Hello,
I wonder, if it´s possible to assign a single task to multiple members of the same project?
If that´s possible, it would be nice to do an individual planning of the hours needed by each member to finish their very own part of the task.
Thank you in advance
If a task is done by two people, why not create two tasks separately and link them to one parent.
Hello Andreas,
Currently, you need to assign a work package to a group to cover multiple assignees. This Epic has received a lot of votes and aims to add new features for this use case in a future release.
The best practice by now would be to follow Madhu's recommendation and split up tasks wherever possible.
Best regards
Alexander
Alexander Stock wrote:
Hello Andreas,
Currently, you need to assign a work package to a group to cover multiple assignees. This Epic has received a lot of votes and aims to add new features for this use case in a future release.
<mention class="mention" data-id="30105" data-type="work_package" data-text="##30105">##30105
The best practice by now would be to follow Madhu's recommendation and split up tasks wherever possible.
Best regards
Alexander
Hello Madhu and Alexander,
Thank you for the information. I pretty much support this as a new feature in upcoming versions.
Best regards
Andreas