Started October 11, 2023 04:36 · 1 reply · 2 participants
I cannot find the progress% column in community edition due I want to check the percentage of the task project (Progress tracking).
Hello Ouk
just a few question to narrow things down:
- Are you tracking progress manually or by status? [1]
- Is the progress field present when you e.g. open a tasks? Can you modify it? (A screenshot would be great)
- Is it possible for your to use progress as an filter option?
Best
Alexander
[1] https://www.openproject.org/docs/user-guide/time-and-costs/progress-tracking/