I cannot find the progress% column in community edition due I want to check the percentage of the task project (Progress tracking).

Message actions

Hello Ouk

just a few question to narrow things down:

  • Are you tracking progress manually or by status? [1]
  • Is the progress field present when you e.g. open a tasks? Can you modify it? (A screenshot would be great)
  • Is it possible for your to use progress as an filter option?

Best

Alexander

[1] https://www.openproject.org/docs/user-guide/time-and-costs/progress-tracking/