Recalculate work packages start date with relations after change

Hi everyone.

I'm looking for a way to recalculate the start dates of tasks that follows another task when the latter is shorted.

Task1: ends on July, 31st.

Task2: follows Task1, starting on August, 1st.

Should I change the end date of Task 1 on July, 20th, Task2 start will remain on August, 1st.

This causes some troubles when the following linked tasks are more than 30, is there a way to make Open Project to "shrink" back Task2 to July, 21st?

Thank you for the attention, hope to hear soon from you.

Cheers!

Cape

Message actions

Hi everyone,

I do have similar issue with my projects: is there a way to automatically recalculate the starting date of a task which follows another task when the last one is shorted?

Thanks in advance.

Best,

G

Message actions

Hello Antonio

this Feature Request sounds very similar to your description. It is currently part of the wish list.
I just added +2 votes for you and Giacomo. Please leave a comment there if you feel any information is missing.

Kind regards

Alexander

Message actions

Hello, this feature could really help us.  It is very difficult to modify the dates in the related tasks manually. 

Thank you in advance.

Jan

Message actions

Hi Jan

I added your vote to feature request OP-11914 and encourage you to add your comment if you want to add something for further specification of this request.

Best

Alexander