Lines in Timelines
Started July 1, 2014 16:24 · 2 replies · 2 participants
Hi Community
On the Timelines of OpenProject(https://www.openproject.org/projects/openproject/timelines/36) we can see OP-1005 (at 2014-07-05) in green with a green line over the whole sheet.
I really would like to know, how to do that.
Is there a Manual where I can read about such things?
Thank you,
Chris
Hi Chris,
you can do this by displaying a work package vertically:
- Navigate to a timeline report.
- Click on “Edit” in the upper right corner.
- Enter the ID of the work package you want to display vertically in the section “Vertical work packages”. (In the case of milestones, the vertical work package is displayed as a line.)
You can take a look at the feature tour but some of the information is outdated.
We will update this in the future.
Best,
Robin
Thank you Robin, it works perfect!