Open link in a new tab

Content

Expand project menu

Auto change "new" --> "in progress" when a comment is added

I'm writing from my company's account and have the following question.

Is it possible to achieve the following:

  • Someone creates a task; status is new
  • Someone different from the author adds a comment
  • Status should now automatically change from new to "in progress"

Thanks for any hints on that topic.

Regards, Thomas

Message actions

Hello Thomas, 

Thank you very much for sharing your question. 

There is a feature request about automated workflows: https://community.openproject.org/projects/openproject/work_packages/37473/activity
I have added a comment with your requirements as well as a vote for you. 

Best regards
Samantha

Message actions

Thanks for that.

Regards, Thomas