How to move / change date of a phase?

Hi,

the help "How to change the order of an item in the Gantt chart?" shows how to modify a phase (e.g. via Gantt chart)

Changing the start date or end date only works as long there are no sub tasks.

However, to move a phase with various epics and tasks, the date values must be changed on all tasks one by one.

Is there a way to move (adjust the date) the complete phase and automatically all sub-tasks will be adjusted?

Cheers

Rainer

Message actions

Hi,

I am not sure whether I alone have to shift or replan a phases in a project?

Is there no simple solution to modify the complete phase?

I had thought that this is a main function of a project planing tool.

many thanks for any hint.

Cheers

Rainer

Message actions

Hi Rainer, you're not the only one. There's a feature request here: OP-7701 

Kind regards

Matthias