Content
Distribute log unit costs equitably in several workpackages
Started December 27, 2019 07:50 · 2 replies · 2 participants
Hello,
I would like to know how I can distribute hours in several workpackages. Example: I spent 8 hours doing 3 workpacges today and I would like Openproject distribute these hours equitably without logging unit cost one by one.
Anybody help me?
Thank you,
Hi Cristian,
OpenProject does not support this yet.
Best
Niels
Oh...
Thanks! ;)