Good afternoon,
It appears, that the Actual unit costs don't summarize and show only the latest unit cost log.
I am sure it worked well in v13, perhaps the new option in settings has been added?
Hello Oleg,
thank you for mentioning this. You did everything right. I am afraid this is in fact a bug and not related to your settings.
Currently, when you open a budget, in the actual unit costs, the last entry just replaces a preceding entry, if both have been booked on the same work package.
So in your example, if you would have booked a unit onto a different work package in this project, using the same budget, that would appear in the list.
Please find here a bug report where this is explained in more detail:
https://community.openproject.org/wp/55895
The costs are not lost though. The value on the right side still sums up correctly (as you highlighted red).
I encourage you to watch the corresponding bug report in order to receive a notification once this is fixed.
Best,
Alexander
Hi Alexander,
Thanks for your detailed clarification and the bug report. I will follow this thread.