Scenario extracted from ###61054
####
Scenario 29: Add children (parent in manual originally; children all manual, mixed working days) 🟢
* Setup
* Start date: Wed, Jan 15, 2025
* Finish date: Fri, Jan 17, 2025
* Duration: 3 2
* Mode: Manual
* Working days only: on
* Relations: none
* Change
* Add child 1:
* 16–20 Jan, 2025
* Working days only: on off
* Duration: 3
* Mode: Manual
* Add child 2:
* 21-26 Jan, 2025
* Working days only: off on
* Duration: 6
* Mode: Manual
* Expected result
* Start date: Thu, Jan 16, 2025
* Finish date: Sun, Jan 26, 2025
* Mode: Automatic (automatically-set when first child is added)
* Working days only: disabled and off
* Duration: 11
* Context: If at least one child has "working days only: off", then the parent also has "working days only: off".
##### **Actual result/Buggy behaviour:**
see here: [https://qa.openproject-edge.com/projects/test-project-cecile/work\_packages?query\_id=3767](https://qa.openproject-edge.com/projects/test-project-cecile/work_packages?query_id=3767)
Start date: Jan 15, 2025
Finish date:Â Jan 17, 2025
Mode: Manual
Working days only: enabled and on
Duration: 3
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/341456/content">
<br>
####
* Setup
* Start date: Wed, Jan 15, 2025
* Finish date: Fri, Jan 17, 2025
* Duration: 3
* Mode: Manual
* Working days only: on
* Relations: none
* Change
* Add child 1:
* 16–20 Jan, 2025
* Working days only: on
* Duration: 3
* Mode: Manual
* Add child 2:
* 21-26 Jan, 2025
* Working days only: off
* Duration: 6
* Mode: Manual
* Expected result
* Start date: Thu, Jan 16, 2025
* Finish date: Sun, Jan 26, 2025
* Mode: Automatic (automatically-set when first child is added)
* Working days only: disabled and off
* Duration: 11
* Context: If at least one child has "working days only: off", then the parent also has "working days only: off".
##### **Actual result/Buggy behaviour:**
see here: [https://qa.openproject-edge.com/projects/test-project-cecile/work\_packages?query\_id=3767](https://qa.openproject-edge.com/projects/test-project-cecile/work_packages?query_id=3767)
Start date: Jan 15, 2025
Finish date:Â Jan 17, 2025
Mode: Manual
Working days only: enabled and on
Duration: 3