**As a** project manager
**I want to** automatically move a set of work packages to the earliest date possible
**So that** I don't have to do this manually.
# Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
# Features
The development is split into its children features. the following features:
Please see description inside each sub-feature. ## ##59539
* ###59539
* ###59540
* ###59845
* ###59541
* ###59542
* ###59731
Some testing scenarios are described here: workPackageValue:59539:status | workPackageValue:59539:version
* ###60670
workPackageValue:59539:description
## ##59540
workPackageValue:59540:status | workPackageValue:59540:version
workPackageValue:59540:description
## ##59541
workPackageValue:59541:status | workPackageValue:59541:version
workPackageValue:59541:description
## ##59542
workPackageValue:59542:status | workPackageValue:59542:version
workPackageValue:59542:description
## ##59731
workPackageValue:59731:status | workPackageValue:59731:version
workPackageValue:59731:description
# Out of scope
* Other scheduling modes and constraints such as "Must start on" or "Start not later than", "Start no earlier than".
* Editable lag in relations tab.
* This will have been addressed by the time we work on this feature: ###22360
**I want to** automatically move a set of work packages to the earliest date possible
**So that** I don't have to do this manually.
# Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
# Features
The development is split into its children features.
Please see description inside each sub-feature.
* ###59539
* ###59540
* ###59845
* ###59541
* ###59542
* ###59731
Some testing scenarios are described here:
* ###60670
## ##59540
workPackageValue:59540:status | workPackageValue:59540:version
workPackageValue:59540:description
## ##59541
workPackageValue:59541:status | workPackageValue:59541:version
workPackageValue:59541:description
## ##59542
workPackageValue:59542:status | workPackageValue:59542:version
workPackageValue:59542:description
## ##59731
workPackageValue:59731:status | workPackageValue:59731:version
workPackageValue:59731:description
* Other scheduling modes and constraints such as "Must start on" or "Start not later than", "Start no earlier than".
* Editable lag in relations tab.
* This will have been addressed by the time we work on this feature: ###22360