As #### Context
The way progress reported is calculated in OpenProejct [was changed](https://www.openproject.org/blog/changes-progress-work-estimates/) in versions 14.0 through 14.2: ##40867. The changes were:
* Renaming of terms:
* Estimated time → Work
* Remaining hours → Remaining work
* Progress (%) % Complete
* Work, Remaining work and % Complete were connected such that updating one would update all the others.
#### Summary
However, a project manager
I want to have new admin settings for finer considerable number of users gave us feedback saying that the were not always ideal, and that they wanted more control and configuration options the ability to manually input % Complete independent of additional calculation methods Work and for project progress reporting Remaining work.
so In this epic, we took that I can enable my project teams user feedback into account and made further changes, also [described in a blog post](https://www.openproject.org/blog/updates-to-progress-tracking-in-14-6-based-on-user-feedback/). Broadly, this epic covers:
* Once again making it possible for users to to manually edit % Complete in work-based mode. mode
* New admin settings for finer control and configuration
#### Features
<figure class="table op-uc-figure_align-center op-uc-figure"><table class="op-uc-table"><tbody><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Feature</strong></p></td><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Released in version</strong></p></td><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Status</strong></p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:status</p></td></tr></tbody></table></figure>
###
The way progress reported is calculated in OpenProejct [was changed](https://www.openproject.org/blog/changes-progress-work-estimates/) in versions 14.0 through 14.2: ##40867. The changes were:
* Renaming of terms:
* Estimated time → Work
* Remaining hours → Remaining work
* Progress (%) % Complete
* Work, Remaining work and % Complete were connected such that updating one would update all the others.
#### Summary
However,
I want to have new admin settings for finer
so
* Once again making it possible for users
* New admin settings for finer control and configuration
#### Features
<figure class="table op-uc-figure_align-center op-uc-figure"><table class="op-uc-table"><tbody><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Feature</strong></p></td><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Released in version</strong></p></td><td class="op-uc-table--cell"><p class="op-uc-p"><strong>Status</strong></p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55997:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55803:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57990:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:57258:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:56363:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:52233:status</p></td></tr><tr class="op-uc-table--row"><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:subject</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:version</p></td><td class="op-uc-table--cell"><p class="op-uc-p">workPackageValue:55802:status</p></td></tr></tbody></table></figure>
###