Updated by Christophe Bliard over 1 year ago
**As a** project manager
**I want to** be able This is part of ##42388, split in smaller chunks to maintain manual scheduling mode when deliver values more often.
This chunk is about adding a dialog when making a work package as a successor
**So that** I don't lose while creating a follows/precedes relation. The dialog ask the dates when I add it as a successor.
#### Acceptance criteria
##### General
* If a user wether the successor work package was previously manually scheduled, but is then added scheduling mode should be kept as a successor. Or if a predecessor is added manual, or should be switched to a manually scheduled work package:
* We will give automatic.
Before that, the user a confirmation dialog with two options (see mockups for text):
* Maintain manual scheduling
* Switch successor is always switched to automatic
#### Visuals automatic.
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for This is described in greater details in the most recent mockups._
**Options when adding a predecessor to a manually scheduled parent work package in Gantt view:** package.
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226792/content"> It can be started only once ##59539 is completed.
**I want to** be able
This chunk is about
**So that** I don't lose
#### Acceptance criteria
##### General
* If a
* We will give
Before that,
* Maintain manual scheduling
* Switch
#### Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for
**Options when adding a predecessor to a manually scheduled