Content
View differences
Updated by Christophe Bliard over 1 year ago
**As a** project manager
**I want to** automatically move a set This is part of work packages ##42388, split in smaller chunks to deliver values more often.
The scope is reduced to the earliest date possible
**So that** I don't have to do this manually. following:
#### Acceptance criteria
##### General
* There are only two scheduling modes. As described in the parent work package:
* **Manual**: The user can freely set the start and finish dates, but relations are ignored. Data is migrated
* **Automatic:** Automatically sets the start date based on a predecessor. The user can only set duration.
* This Automatic mode is also used works for parents, where the duration field is also inactive.
* Any time a user wants to manually choose dates for a successor work package, they select manual scheduling.
* By default, all new work packages will be manually scheduled.
* A new manually-scheduled work package will either have no dates, or take and sets the current date (depending on existing settings).
* Every newly created work package will have no predecessor; they have to be added later.
* If it's a new child work package, it will continue behaving as it does today and by default take soon as possible given the parent's start date.
* For automatic scheduling, a predecessor is required. If there are no predecessors and automatic mode is selected in the date picker:
* the top banner will show an error informing the user that a predecessor is required
* save action and all fields will be disabled (non-working days, dates...)
* If a Automatic mode for parent work package was previously manually scheduled, but is then added as a successor. Or if a predecessor is added to a manually scheduled work package:
* the scheduling mode of the successor will always change to automatic. packages
**Parent/children relations** Not included in this scope is:
* Parents will continue to behave as it does today, except they will now be Having tabs in Automatic mode.
* They "cover" the date ranges of picker with the two children predecessors, successors, and children can have an indirect link to relationships of the parents.
information
* Their dates The tab line is not displayed at all. The automatic scheduling logic will not be editable.
* They can be switched to manual mode.
* Adding a child to a manually-scheduled work package will automatically move as expected, but the parent to automatic mode.
* If the parent previously had dates, those user will be overwritten by those of have limited relations information available from the children. top banner only.
* If Adding the child does not yet have dates, neither will the parent. Previous dates (before being a parent) are lost, as tabs is the case today. handled in ##59540.
* Removing the last child of Having a parent will switch the now non-parent dialog when moving an automatically scheduled work package mode to manual, whilst preserving dates before on the removal of the last child. Gantt chart
* If neither the child nor the parent had dates, it It will simply be switched to manual mode without any dates.
* A dialog will be added in feature #59542 to give more options.
##### Gantt view
* You can freely move manually scheduled work packages.
* It's impossible to move an automatically scheduled successor
* A dialog will be added in feature #59541 to give more options.
* For work packages without any predecessors, it will not be possible to select Automatic mode.
* Clicking package on "Automatic" will show a blankslate with no actions possible.
* If the dates of a predecessor of an automatically scheduled work package are removed, Gantt chart. To move it, the successor will go into manual mode. But we need to ask the user for confirmation:
* "This work package has at least one automatically scheduled successor. Removing to change the dates here will switch the successor to manual scheduling mode to preserve its dates." manual, or change the lag of the relation.
* TODO: move this Adding a dialog to a new chunk 5
* If all predecessors of an automatically scheduled work package are deleted:
* The "successor" goes into manual mode. We will ask for if the user confirmation:
* "This work package has at least one automatically scheduled successor. Deleting this work package will switch the successor wants to manual scheduling to preserve its dates."
* TODO: move this to a new chunk 5
* The relation is deleted
##### **Migration from an earlier version**
* Dates will **NOT** change automatically. All existing dates are preserved.
* For work packages with no predecessors (or with no relations at all), they will be switched to manual scheduling.
* These work packages are switched to manual scheduling regardless of having dates or not. change lag is handled in ##59541.
* When relations exist,
* If there was Having a gap in dialog when making a predecessor/successor relationship, the successor will be set to “Automatic" with a lag set for the follows/precedes relation with the closest predecessor (the one that finishes latest).
* In a multi-relationship situation, earlier predecessors that do not affect manual work package being the date of the successor do not have lag added.
* If the relation exists but there are no dates, they will be switched to manual The scheduling mode.
* If the relationship is parent-child, there are no changes to dates; the parent remains in automatic mode (as is of the case now) and the children follow the rules above.
* Manually scheduled work packages remain so.
##### **Date picker**
* The date picker successor will be Primerised.
* There is a new segmented control with label "Scheduling mode"
* There is a help icon next always change to the label. On hover, it displays a tooltip with this text: "‘Manual’ lets you pick fixed dates freely but ignores all predecessors. ‘Automatic’ selects the earliest possible start date for this work package, which cannot be modified." automatic.
* Options: "Manual" and "Automatic"
* The "Working days only" toggle becomes Adding a checkbox aligned dialog to ask if the far right edge of the same line as the segmented control.
* In **Manual** mode:
* The dates are freely selectable, without restrictions.
* Relations don't affect the start and finish dates.
* A manually scheduled work package can push and pull successors that are automatically scheduled
* A user wants to keep manual work package can start before any of their predecessors
* A manually scheduled work package will not push a predecessor scheduling or switch to the past when it's moved to the past
* In **Automatic** mode:
* The _Start date_ and _Finish date_ fields are read-only
* The "Today" links under the date fields are disabled (but not removed so that elements in the date picker don't move when changing modes)
* Duration remains editable (unless it's a parent)
* The mini calendar goes into read-only mode
##### **Date picker banners:**
**Manual scheduling:**
* Colour: Warning orange
* Action: Show relations
* Case 1: Relations exist but no predecessors.
* **Manually scheduled. Dates not affected by relations.**
Click on “Show relations” for Gantt overview
* Case 2: There are predecessors but a gap of over two days with the finish date of the latest predecessor.
* **Manually scheduled. Dates not affected by relations.**
There is a gap between this and all predecessors.
* Case 3: There are predecessors and the current work package overlaps with at least one of them.
* **Manually scheduled. Dates not affected by relations.**
Overlaps with at least one predecessor.
* Case 4: Work package has children.
* **Manually scheduled. Dates not affected by relations.**
This has child work package but their start dates are ignored.
**Automatic:**
* Colour: Info blue
* Action: Show relations
* Case 1: There is a predecessor.
* **The start date is set by a predecessor.**
Click on “Show relations” for Gantt overview.
* Case 4: The work package is a parent.
* **The dates are determined by child work packages.**
Click on “Show relations” for Gantt overview.
* If a work package is both a parent and has predecessors, this "parent" message automatic scheduling will be displayed.
#### Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
**Manual scheduling (but predecessors overlap):**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226779/content">
**As soon as possible (start date set by predecessors):**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226780/content">
<br> handled in ##59542.
**I want to** automatically move a set
The scope is reduced to
**So that** I don't have to do this manually.
#### Acceptance criteria
##### General
* There are only two scheduling modes.
* **Manual**: The user can freely set the start and finish dates, but relations are ignored.
* **Automatic:** Automatically sets the start date based on a predecessor. The user can only set duration.
* This
* Any time a user wants to manually choose dates for a
* By default, all new work packages will be manually scheduled.
* A new manually-scheduled work package will either have no dates, or take
* Every newly created work package will have no predecessor; they have to be added later.
* If it's a new child work package, it will continue behaving as it does today and by default take
* For automatic scheduling, a predecessor is required. If there are no predecessors and automatic mode is selected in the date picker:
* the top banner will show an error informing the user that a predecessor is required
* save action and all fields will be disabled (non-working days, dates...)
* If a
* the scheduling mode of the successor will always change to automatic.
**Parent/children relations**
* Parents will continue to behave as it does today, except they will now be
* They "cover" the date ranges of
* They can be switched to manual mode.
* Adding a child to a manually-scheduled work package will automatically move
* If the parent previously had dates, those
* If
* Removing the last child of
* If neither the child nor the parent had dates, it
* A dialog will be added in feature #59542 to give more options.
##### Gantt view
* You can freely move manually scheduled work packages.
* It's impossible to move an automatically scheduled successor
* A dialog will be added in feature #59541 to give more options.
* For work packages without any predecessors, it will not be possible to select Automatic mode.
* Clicking
* If the dates of a predecessor of an automatically scheduled work package are removed,
* "This work package has at least one automatically scheduled successor. Removing
* TODO: move this
* If all predecessors of an automatically scheduled work package are deleted:
* The "successor" goes into manual mode. We will ask for
* "This work package has at least one automatically scheduled successor. Deleting this work package will switch the successor
* TODO: move this to a new chunk 5
* The relation is deleted
##### **Migration from an earlier version**
* Dates will **NOT** change automatically. All existing dates are preserved.
* For work packages with no predecessors (or with no relations at all), they will be switched to manual scheduling.
* These work packages are switched to manual scheduling regardless of having dates or not.
* When relations exist,
* If there was
* In a multi-relationship situation, earlier predecessors that do not affect
* If the relationship is parent-child, there are no changes to dates; the parent remains in automatic mode (as is
* Manually scheduled work packages remain so.
##### **Date picker**
* The date picker
* There is a new segmented control with label "Scheduling mode"
* There is a help icon next
* Options: "Manual" and "Automatic"
* The "Working days only" toggle becomes
* In **Manual** mode:
* The dates are freely selectable, without restrictions.
* Relations don't affect the start and finish dates.
* A manually scheduled work package can push and pull successors that are automatically scheduled
* A
* A manually scheduled work package will not push a predecessor
* In **Automatic** mode:
* The _Start date_ and _Finish date_ fields are read-only
* The "Today" links under the date fields are disabled (but not removed so that elements in the date picker don't move when changing modes)
* Duration remains editable (unless it's a parent)
* The mini calendar goes into read-only mode
##### **Date picker banners:**
**Manual scheduling:**
* Colour: Warning orange
* Action: Show relations
* Case 1: Relations exist but no predecessors.
* **Manually scheduled. Dates not affected by relations.**
Click on “Show relations” for Gantt overview
* Case 2: There are predecessors but a gap of over two days with the finish date of the latest predecessor.
* **Manually scheduled. Dates not affected by relations.**
There is a gap between this and all predecessors.
* Case 3: There are predecessors and the current work package overlaps with at least one of them.
* **Manually scheduled. Dates not affected by relations.**
Overlaps with at least one predecessor.
* Case 4: Work package has children.
* **Manually scheduled. Dates not affected by relations.**
This has child work package but their start dates are ignored.
**Automatic:**
* Colour: Info blue
* Action: Show relations
* Case 1: There is a predecessor.
* **The start date is set by a predecessor.**
Click on “Show relations” for Gantt overview.
* Case 4: The work package is a parent.
* **The dates are determined by child work packages.**
Click on “Show relations” for Gantt overview.
* If a work package is both a parent and has predecessors, this "parent" message
#### Visuals
_**Note:** Please check_ [_Figma_](https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641) _for the most recent mockups._
**Manual scheduling (but predecessors overlap):**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226779/content">
**As soon as possible (start date set by predecessors):**
<img class="image_resized op-uc-image op-uc-image_inline" style="width:540px;" src="/api/v3/attachments/226780/content">
<br>