**As** a project manager/team manager
**I would like** to automatically reschedule all successors when planing to finish a predecessor earlier
**so that** changing the finish date of a predecessor is a reversible action. I don't have to move all successors manually.
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/240496/content"></div></figure> **Acceptance criteria**
* There is a new scheduling mode "Start as soon as possible".
* When this mode is activated users can not manually change the date of this work package in the date picker, team planner or Gantt view.
* In case the user wants to change the date the user needs to switch to the manual scheduling mode first.
* ##22360
* ##42388
**Former scenario description**
> * Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
>
> * After moving Task A to end on Monday Task B begins on Tuesday.
>
> * Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually.
>
> * In case there is an explicitly set slack this slack remains unchanged when rescheduling.
>
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/240497/content"> src="/api/v3/attachments/91565/content">
**I would like** to automatically reschedule all successors when planing to finish a predecessor earlier
**so that** changing the finish date of a predecessor is a reversible action. I don't have to move all successors manually.
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/240496/content"></div></figure>
* When this mode is activated users can not manually change the date of this work package in the date picker, team planner or Gantt view.
* In case the user wants to change the date the user needs to switch to the manual scheduling mode first.
* ##22360
* ##42388
**Former scenario description**
> * Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
>
> * After moving Task A to end on Monday Task B begins on Tuesday.
>
> * Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually.
>
> * In case there is an explicitly set slack this slack remains unchanged when rescheduling.
>