**As** a project manager/team manager
**I want to** I would like to automatically reschedule the follower when planing to finish the predecessor earlier
**so that** changing the finish date of a predecessor is a reversible action. I don't have to move all predessors manually.
**Acceptance criteria**
* There is a new The date of followers can only be edited in the manual scheduling mode "Start as soon as possible". mode.
* When this mode is activated users can not manually change the The start date of this work package in followers is automatically rescheduled based on the date picker, team planner or Gantt view. predecessors. The implicit scheduling mode is "as soon as possible".
* In case the user wants to change the date picker we explain why the user needs to switch to the manual scheduling mode first. dates can not be changed for followers.
* ##22360
* ##42388 ##22360
**Former scenario description**
> * Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
>
> * After moving Task A to end on Monday Task B begins on Tuesday.
>
> * Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually.
>
> * In case there is an explicitly set slack this slack remains unchanged when rescheduling.
>
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/91565/content">
**I want to** I would like to automatically reschedule the follower when planing to finish the predecessor earlier
**so that** changing the finish date of a predecessor is a reversible action. I don't have to move all predessors manually.
**Acceptance criteria**
* There is a new
* When this mode is activated users can not manually change the
* In case the user wants to change the date
* ##22360
* ##42388
**Former scenario description**
> * Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
>
> * After moving Task A to end on Monday Task B begins on Tuesday.
>
> * Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually.
>
> * In case there is an explicitly set slack this slack remains unchanged when rescheduling.
>
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/91565/content">