Updated by Niels Lindenthal over 2 years ago
**As** a project manager/team manager
**I want to** I would like to automatically reschedule the successor when planing to finish the predecessor earlier
**so that** I don't have to do this manually.
**Acceptance criteria**
* Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
* After moving Task A to end on Monday Task B begins on Tuesday.
* Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually. manually.
* **\[open\]** When moving Task A to end on Monday, keep the slack intact (move B to begin on Wednesday) or eat up the slack (move B to begin on Tuesday), or leave the the successor where it was because it was done manually (B would still begin on Thursday)
* NL: In case there is a explicitly set slack this slack is persisted when rescheduling.
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/91565/content">
**I want to** I would like to automatically reschedule the successor when planing to finish the predecessor earlier
**so that** I don't have to do this manually.
**Acceptance criteria**
* Scenario 1: Task B (begins on Wednesday) follows Task A (ends on Tuesday). There are no other constraints or non-working days that impact the scheduling.
* After moving Task A to end on Monday Task B begins on Tuesday.
* Scenario 2: Task B (begins on Thursday) follows Task A (ends on Tuesday). There are no other constraints or non working days. There is a one day slack that was added manually.
* **\[open\]** When moving Task A to end on Monday, keep the slack intact (move B to begin on Wednesday) or eat up the slack (move B to begin on Tuesday), or leave the the successor where it was because it was done manually (B would still begin on Thursday)
* NL: In case there is a explicitly set slack this slack is persisted when rescheduling.
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/91565/content">