Updated by Christophe Bliard over 2 years ago
See ##40867 for the full picture.
Work and Remaining Work fields must be editable for any work package, regardless of having a child or not. not.
* when "Work" is set to 0h, value should be unset (set to `nil`), and "Remaining Work" should be unset as well
* when "Remaining Work" is set to 0h, it should stay 0h. It cannot be set to 0h if "Work" is not set.
Questions
* Should setting Work update Remaining Work?
* Should setting Remaining Work update Work?
* Note: currently, this behavior is only present if the type of the work package is the one identified as a Task type in the backlogs plugin settings.
Work and Remaining Work fields must be editable for any work package, regardless of having a child or not.
* when "Work" is set to 0h, value should be unset (set to `nil`), and "Remaining Work" should be unset as well
* when "Remaining Work" is set to 0h, it should stay 0h. It cannot be set to 0h if "Work" is not set.
Questions
* Should setting Work update Remaining Work?
* Should setting Remaining Work update Work?
* Note: currently, this behavior is only present if the type of the work package is the one identified as a Task type in the backlogs plugin settings.