Updated by Christophe Bliard over 2 years ago
See ##40867 for the full picture.
Work, Remaining Work and % Complete fields must be editable for any work package, regardless of having a child or not. (Before that, the work, remaining work and the % complete of a work package with children could not be edited)
* when "Work" is set to 0h, value should be unset (set set to `nil`), and "Remaining Work" should be unset as well \`nil\`
* when "Remaining Work" is set to 0h, it should stay 0h. It cannot be set to 0h if "Work" is not set.
Questions
* Should setting Work set Remaining Work?
* Should setting Remaining Work set Work?
Work, Remaining Work and % Complete fields must be editable for any work package, regardless of having a child or not. (Before that, the work, remaining work and the % complete of a work package with children could not be edited)
* when "Work" is set to 0h, value should be unset (set
* when "Remaining Work" is set to 0h, it should stay 0h. It cannot be set to 0h if "Work" is not set.
Questions
* Should setting Work set Remaining Work?
* Should setting Remaining Work set Work?