Updated by Niels Lindenthal almost 4 years ago
### **Environment**:
**OpenProject 12.2 RC**
### Current behavior and steps to reproduce
<img **<img class="op-uc-image op-uc-image_inline" style="width:697px;" src="/api/v3/attachments/36001/content"> src="/api/v3/attachments/35993/content">**
[https://niels.openproject-edge.com/projects/progress-calculation-1/work\_packages?query\_id=338](https://niels.openproject-edge.com/projects/progress-calculation-1/work_packages?query_id=338)
1. Unset estimated time ("-" is currently (12.1) are included into the calculation by 8 h. This is completely unclear to almost all user. It is also not documented. unclear.
Example: _Grandchild 1.1.2_ has an implicit estimated time of 8 h. This Grandchild 1.1.2 which leads to a Progress % for Child 1.1 calculated value of 50 %. Since the The correct way would be to not include any estimated time for _Grandchild 1.1.2_ is "0" it must not be included into the progress calculation of Child 1.1. this child work package.
2. It is not possible to set a percentage % for a parent work package.
Example: The estimated time for Child 1.1 itself is 16 8 h. It is not possible to define Progress % for those 16 8 h.
## Expected behavior
Calculation logic: https://nextcloud.openproject.org/index.php/s/j45k7oqPo2R2iot
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/36002/content"> src="/api/v3/attachments/35994/content">
* Unset estimated time is included by 0 h into the calculation (not 8 h).
* It is possible to set the Progress % for the estimated time of a parent work packages. package.
* Unset estimated time is included by 0 h into the calculation (not 8 h).
* The Progress % value calculated for children work packages are indicated in brackets (similar to estimated time).
## Visuals
https://www.figma.com/file/iVzhExjBr2fmOpYTEwYZYU/Progress-representation?node-id=9%3A5459
**OpenProject 12.2 RC**
### Current behavior and steps to reproduce
<img
[https://niels.openproject-edge.com/projects/progress-calculation-1/work\_packages?query\_id=338](https://niels.openproject-edge.com/projects/progress-calculation-1/work_packages?query_id=338)
1. Unset estimated time ("-" is currently (12.1)
Example: _Grandchild 1.1.2_ has an implicit estimated time of 8 h. This
2. It is not possible to set a percentage % for a parent work package.
Example: The estimated time for Child 1.1 itself is 16
## Expected behavior
Calculation logic: https://nextcloud.openproject.org/index.php/s/j45k7oqPo2R2iot
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/36002/content">
* Unset estimated time is included by 0 h into the calculation (not 8 h).
* It is possible to set the Progress % for the estimated time of
*
*
## Visuals
https://www.figma.com/file/iVzhExjBr2fmOpYTEwYZYU/Progress-representation?node-id=9%3A5459