Updated by Niels Lindenthal almost 4 years ago
### **Environment**:
Your OpenProject Version: **OpenProject 12.2 RC** 12.0.7**
Operating System / Browser / OpenProject language: Windows 10 / Chrome 91.0.4472.77, Edge 91.0.864.41, Chrome portable, Firefox 88.0.1 / OpenProject language: Русский, English
### Current behavior and steps **Logs**
No errors
### **Steps to reproduce reproduce:**
**<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/35993/content">**
1. Unset estimated time are included into the calculation by 8 h. This is completely unclear.
Example: Grandchild 1.1.2 which leads Go to calculated value of 50 %. The correct way would be to not include any estimated time for this child work package. page Work Packages
2. It is not possible to set a percentage % Create 1 Task with 2 SubTask and for a parent work package.
Example: The estimated time SubTask create 2extra SubSub task
3. Select wrong progress for Child 1.1 itself is 8 h. It is not possible to define Progress % Parent Task
### **Actual Behavior**
Now progress for those 8 h. Task 40%
## Expected behavior <figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27109/content"></div></figure>
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/35994/content"> ### **Expected Behavior**
* It is possible to set the Progress % should be 30% because Task include two SubTasks they will cost for the estimated time task like 50% from progress. Task progress= 50% of a parent work package.
* Unset estimated time is included by progress from SubTask 1 + 50% of progress from SubTask 2 = 50% from 0 h into the calculation (not 8 h).
* The value calculated for children work packages are indicated in brackets (similar to estimated time). + 50% from 60 = 30%
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27114/content"></div></figure>
No errors
### **Steps
**<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/35993/content">**
1. Unset estimated time are included into the calculation by 8 h. This is completely unclear.
Example: Grandchild 1.1.2 which leads
2. It is not possible to set a percentage %
Example: The estimated time
3. Select wrong progress
### **Actual Behavior**
Now progress
## Expected behavior
<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/35994/content">
* It is possible to set the Progress %
* Unset estimated time is included by
* The value calculated for children work packages are indicated in brackets (similar to estimated time).
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27114/content"></div></figure>