Content
View differences
Updated by Niels Lindenthal over 4 years ago
**As a** project manager
**I want to** enter a project deadline and plan backwards
**So that** I know when I have to start the first task.
## Project schedule type start/finish date and project setting "Schedule from"
* A project can have a start date and a finish date:
* There is the new project setting "Schedule from".
* Schedule from: Project start date
* Schedule from: Project finish date
* Schedule from: No project start and finish date
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27176/content"></div></figure>
## Schedule projects based on defined schedule type
* Automatic calculation of the project start dates and finish dates depending on project scheduling mode.
* When the project is scheduled from the project start date the finish date is derived (inactive form field). (inactive). This date can be changed. The project schedule is updated accordingly.
* When the project is scheduled from the project finish date the start date is derived (inactive form field). (inactive). The project schedule is updated accordingly.
* The project scheduling mode can be changed for an existing project schedule.
## Project list and project dashboard
project.
* Show the project start date and project finish date in the project list.
* Show the project start date and project finish date in the project overview dashboard.
## Schedule based Constraint types on work package's constraint type packages
* Work packages have a We introduce the concept of the following constraint type:
* As soon as possible
* As late as possible
* Project schedules are based on work package's constraint type
## Date picker modal
* See and change view to CRUD the work package's constraint type. type
* The List view to CRUD the constraint type can only be set for automatically scheduled work packages.
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27175/content"></div></figure>
## Gantt chart Scheduling
* Show Adapt the constraint type in a separate column. Clicking it opens scheduling logic to respect the date picker modal. project settings "Schedule from".
* Adapt the Gantt view for scheduling logic to respect the new scenarios.
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27174/content"></div></figure> work package's constraint type.
**I want to** enter a project deadline and plan backwards
**So that** I know when I have to start the first task.
## Project schedule type
* A project can have a start date and a finish date:
* There is the new project setting "Schedule from".
* Schedule from: Project start date
* Schedule from: Project finish date
* Schedule from: No project start and finish date
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27176/content"></div></figure>
## Schedule projects based on defined schedule type
* When the project is scheduled from the project start date the finish date is derived (inactive form field).
* When the project is scheduled from the project finish date the start date is derived (inactive form field).
* The project scheduling mode can be changed for an existing project schedule.
## Project list and project dashboard
* Show the project start date and project finish date in the project overview dashboard.
## Schedule based
* Work packages have a
* As soon as possible
* As late as possible
* Project schedules are based on work package's constraint type
## Date picker modal
* See and change
* The
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27175/content"></div></figure>
## Gantt chart
* Show
* Adapt the Gantt view for
<figure class="image op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/27174/content"></div></figure>