Updated by Henriette Darge over 4 years ago
### **Environment**:
Your OpenProject Version: **11.3.4**
Operating System / Browser / OpenProject language: **Windows 10, Chrome, English**
### **Logs**
N/A
### **Steps to reproduce:**
1. Create Click to create a new Work Package of type milestone (take care that the type really is marked as "Milestone" in the administration).
2. Have a look at the Click on date field
### **Actual Behavior**
* In the date field, (where it says "no start date - no finish date"
* date")
3. Date popup only allows selecting one date.
### **Expected **Actual Behavior**
* In Despite the date field new milestone form implying that I should be written "no date" because you can able to set a start and finish date, it does not actually allow me to do so. Every date change I make changes only select one the start date.
Adding relations to other tasks also does not display a finish date in the milestone.
It is unclear what effect toggling "manual scheduling" has on anything here - the checkbox appears to do nothing at all.
### **Expected Behavior**
I expect that I should be able to either set a finish date for a Milestone (and not a start and a finished date) milestone, or it should be inferred from the related tasks. Neither of these appear to be possible at the moment.
Your OpenProject Version: **11.3.4**
Operating System / Browser / OpenProject language: **Windows 10, Chrome, English**
### **Logs**
N/A
### **Steps to reproduce:**
1. Create
2. Have a look at the
### **Actual Behavior**
* In the date field,
*
3.
### **Expected
* In
Adding relations to other tasks also does not display a finish
It is unclear what effect toggling "manual scheduling" has on anything here - the checkbox appears to do nothing at all.
### **Expected Behavior**
I expect that I should be able to either set a finish date