Updated by Lucas Knechtel 25 days ago
**As **As** a project manager** manager using baselines to track progress and deviations, I
**I want to to** see one or more selected baselines rendered as additional bars directly in the Gantt chart,
**so that** so that I can identify schedule deviations (ahead of / behind plan) at a glance without opening the work package list details.
**Acceptance criteria**
* In the Gantt view, the user can activate a baseline overlay via the existing baseline selection.
* For each work package, the baseline is displayed as a second bar next to (e.g. below) the current work package bar.
* The overlay also applies to milestones (and phases), so that milestone shifts against the baseline are visible directly in the chart.
* The user can freely choose which baseline to display (e.g. "yesterday", "last working day", a specific date, or a saved baseline).
* It is possible to display and compare multiple baselines simultaneously (e.g. Baseline 1 and Baseline 2 next to the current bar). When multiple baselines are shown, there is a clear arrangement (stacking order, row height) and visual distinction between them (e.g. different grey shades plus a legend), so that a trend across several baseline dates remains recognizable at a glance.
* The baseline bar(s) are styled in grey and/or semi-transparent to be clearly distinguishable from the current (colored) plan bar.
* Each baseline bar is positioned exactly at its original start and finish date; the current bar remains unchanged.
* Deviations are immediately recognizable: if the current bar starts/ends earlier or later than the baseline bar, this is visible without any additional interaction.
* The direction of the deviation (ahead of / behind plan) is visually indicated (e.g. via color coding or a delta connector between the baseline finish and the current finish), and the deviation in days is shown in the bar's tooltip.
* The overlay works consistently with existing Gantt features (zoom levels, collapsing/expanding, filtering). filtering)
* Work packages without baseline values (e.g. created after the baseline date) show no baseline bar.
**Technical notes**
* Reference for expected UX: Jira Advanced Roadmaps baseline display (screenshot see activity tab). tab)
**Permissions and visibility considerations**
* To _To whom is this feature visible? visible?_
* To _To all users who have permission to view the Gantt chart / work packages of the project; the baseline overlay follows the same visibility rules as the existing baseline function in the work package table. table._
* When _When is it not visible? visible?_
* When _When no baseline is selected/activated, when the user lacks permission to view the work packages, or for work packages that have no data for the selected baseline date. date._
**Translation considerations**
* Key _Key terms and phrases in the key languages languages_
* "Show baseline in Gantt chart" (EN) / "Baseline im Gantt-Diagramm anzeigen" (DE)
* Tooltip labels such as "Original start date" / "Ursprüngliches Startdatum" and "Original finish date" / "Ursprüngliches Enddatum"
* Deviation labels such as "Deviation" / "Abweichung", "ahead of plan" / "vor Plan" and "behind plan" / "hinter Plan"
**Out of scope**
* Changes to the existing baseline display in the work package list/table.
* Automatic scheduling or re-planning based on baseline deviations.
* Baseline variance reports/exports (numeric deviation reports beyond the visual overlay); the in-bar tooltip deviation in days is part of the visual overlay and not considered a separate report. overlay).
* Editing or moving the baseline bars (baselines remain read-only). read-only
**I
**so that**
**Acceptance criteria**
* In the Gantt view, the user can activate a baseline overlay via the existing baseline selection.
* For each work package, the baseline is displayed as a second bar next to (e.g. below) the current work package bar.
* The overlay also applies to milestones (and phases), so that milestone shifts against the baseline are visible directly in the chart.
* The user can freely choose which baseline to display (e.g. "yesterday", "last working day", a specific date, or a saved baseline).
* It is possible to display and compare multiple baselines simultaneously (e.g. Baseline 1 and Baseline 2 next to the current bar). When multiple baselines are shown, there is a clear arrangement (stacking order, row height) and visual distinction between them (e.g. different grey shades plus a legend), so that a trend across several baseline dates remains recognizable at a glance.
* The baseline bar(s) are styled in grey and/or semi-transparent to be clearly distinguishable from the current (colored) plan bar.
* Each baseline bar is positioned exactly at its original start and finish date; the current bar remains unchanged.
* Deviations are immediately recognizable: if the current bar starts/ends earlier or later than the baseline bar, this is visible without any additional interaction.
* The direction of the deviation (ahead of / behind plan) is visually indicated (e.g. via color coding or a delta connector between the baseline finish and the current finish), and the deviation in days is shown in the bar's tooltip.
* The overlay works consistently with existing Gantt features (zoom levels, collapsing/expanding, filtering).
* Work packages without baseline values (e.g. created after the baseline date) show no baseline bar.
**Technical notes**
* Reference for expected UX: Jira Advanced Roadmaps baseline display (screenshot see activity tab).
**Permissions and visibility considerations**
* To
* To
* When
* When
**Translation considerations**
* Key
* "Show baseline in Gantt chart" (EN) / "Baseline im Gantt-Diagramm anzeigen" (DE)
* Tooltip labels such as "Original start date" / "Ursprüngliches Startdatum" and "Original finish date" / "Ursprüngliches Enddatum"
* Deviation labels such as "Deviation" / "Abweichung", "ahead of plan" / "vor Plan" and "behind plan" / "hinter Plan"
**Out of scope**
* Changes to the existing baseline display in the work package list/table.
* Automatic scheduling or re-planning based on baseline deviations.
* Baseline variance reports/exports (numeric deviation reports beyond the visual overlay); the in-bar tooltip deviation in days is part of the visual overlay and not considered a separate report.
* Editing or moving the baseline bars (baselines remain read-only).