Content
12.3.0
Overview
100% Total progress
116 closed (100%) 0 open (0%)
Estimates and progress
| Work | 388.00 hours |
Related work packages
-
Duration: analyse requirements and develop UX concept
-
Non-working days: analyse requirements and develop UX concept
-
Update user and admin guides to include duration and non-working days
-
Quick-add menu not showing on smaller screens
-
Editing work packages with existing duration results in a validation error
-
Filters are not working after adding a custom field with default value
-
Duration error message when trying to create a work package with dates
-
Can't delete WPs from board view
-
Insufficient contrast ratio between activity font color and background
-
SystemStackError (stack level too deep) when trying to assign new parent or children to a work package
- Show work packages