Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Tasks dependecies on the same date

Tasks dependecies on the same date

Added by Ed Straker almost 7 years ago

Hi…

I’ve not found something about it in this forum and in documentation and I’m here to ask an help.
My problem is about the fact I have two tasks and one requests 4 hour to be closed and other another 4 hours to be closed.
The second depends of the first one and totally, 4+4 hours are 8 hours, a single day.
If I connect the second one as successors of the first one, OpenProject shift the date of the second to the day after the first one, but it’s wrong, they must keep the same date.
How to do it? Is there a way to obtain it?
Thanks a lot


Replies (1)

RE: Tasks dependecies on the same date - Added by Robin Wagner almost 7 years ago

Hi Ed,

it is not possible to schedule 2 tasks which have a follows-precedes relationship on the same day. The minimum unit for scheduling are days. Therefore, a task which follows another task will always start at least one day later.
To schedule 2 tasks on the same day, you need to remove the follows-precedes relationship.

Robin