Added by Avi Reem over 6 years ago
Hello,
When setting an activity to follow a milestone, the activity starts the following day. As far as I understand it, a milestone has a duration of 0, so I would have expected the activity to start on the same day. Can anyone please advise if this is some setting that I’m missing?
Thanks in advance,
Avi.