Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Development
  1. OpenProject
  2. Forums
  3. Development
  4. Start and finish periods

Start and finish periods

Added by K T over 7 years ago

Hello,

I have two questions about establishing start and finish dates.

  1. Very often, we make the sequence of tasks which could finish and start at the same day or when one task could start the same day as predecessor has finished.
  2. Also, when I establish a connection between these tasks, the system automatically changes the finish date of a predecessor and the start date of a successor. And it could be only two days in the row. That way makes some problems with the calculation of the real duration of the project and I have to do additional work by deleting these dates.

Do you have a plan to change that situation? For example, to give the possibility to denote the hours of a start and the end of the tasks.