I have two questions about establishing start and finish dates.
Very often, we make the sequence of tasks which could finish and start at the same day or when one task could start the same day as predecessor has finished.
Also, when I establish a connection between these tasks, the system automatically changes the finish date of a predecessor and the start date of a successor. And it could be only two days in the row. That way makes some problems with the calculation of the real duration of the project and I have to do additional work by deleting these dates.
Do you have a plan to change that situation? For example, to give the possibility to denote the hours of a start and the end of the tasks.