Start and finish periods
Added by K T about 7 years ago
Hello,
I have two questions about establishing start and finish dates.
- Very often, we make the sequence of tasks which could finish and start at the same day or when one task could start the same day as predecessor has finished.
- Also, when I establish a connection between these tasks, the system automatically changes the finish date of a predecessor and the start date of a successor. And it could be only two days in the row. That way makes some problems with the calculation of the real duration of the project and I have to do additional work by deleting these dates.
Do you have a plan to change that situation? For example, to give the possibility to denote the hours of a start and the end of the tasks.