How to split Costs by year for a Work Package
Added by Deleted user about 7 years ago
Hi,
If we say a work package costs 40 000€ and the start date is in 2017 and the end date is in 2020 and we will give 10 000€ each year.
How could we represent this? The two solutions I think of is to :
1) create different work packages, each package linked to a different annual budget (budget 2017, budget 2018, …) and each task link to a cost of 10 000€.
2) create only one work package but use custom attributes to specify a cost by year (there will be several new columns budget 2017, budget 2018, …) but this won’t be part of the Costs plugin
There is clearly a lack of feature but, for now, how could one split costs into several budgets for one work package?
Thanks in advance