Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. [SOLVED] Calculation of progress

[SOLVED] Calculation of progress

Added by Jörg Panthöfer almost 9 years ago

Hello,

in release 5.0.19 I’ve created a phase with 2 related tasks. All tasks have been completed to 100. For the phase is calculated 150 completion instead of 100%.

This allows the status of the phase can not be set to completed. Here, the error message “The work package was due to the following error can not be saved:. Progress (%) is not set to an allowable value”.

Can someone explain how this is to understand please or maybe is it a bug?

Best regards
Jörg Panthöfer


Replies (3)

RE: Calculation of progress - Added by Oliver Günther almost 9 years ago

Hi Jörg,

there was an issue in both 5.0.18 5.0.19 concerning the normalization of progress values. The issue stems from having children with estimated hours set.
As a workaround: If you remove the estimated hours from the descendants, the progress should be updated correctly.

Parts of the bug was fixed in 5.0.19, but the normalization was still incorrect.

Original bug report: https://community.openproject.com/work_packages/23251/activity
It contains a lot of information on how progress is actually computed for the parent.

The bug was fixed for 6.0.0 in https://community.openproject.com/work_packages/23627/activity

Best,
Oliver

RE: Calculation of progress - Added by Jörg Panthöfer almost 9 years ago

Hi Oliver,

thank you for the info. I have an update on release 6.0.0 installed - it works.

Best,
Jörg

RE: Calculation of progress - Added by Oliver Günther almost 9 years ago

Hey Jörg,

great to hear! :-)

Best,
Oliver