Added by Sebastian Leopold over 8 years ago
Is it possible to assign a percentage of done to a specific workpackage state?
Hi Sebastian,
yes you can:
Administration -> System settings -> Work package tracking -> Calculate the work package done ratio with -> Use the work package status.
Here you can change the percentage done for each status:
Administration -> Work package status -> “Status” -> Progress %.
Regards Niels
Replies (1)
Hi Sebastian,
yes you can:
Administration -> System settings -> Work package tracking -> Calculate the work package done ratio with -> Use the work package status.
Here you can change the percentage done for each status:
Administration -> Work package status -> “Status” -> Progress %.
Regards
Niels